ConstructionWhen you’re in the midst of major construction projects simultaneously occurring at three different locations hundreds of miles apart from one another, what is one of the best phrases you can hear? “We’re on schedule!”

That’s the case with our three new State Veterans Homes being built in the communities of Bemidji, Montevideo and Preston. Following successful groundbreakings hosted by the Minnesota Department of Veterans Affairs (MDVA) last summer and a long, mild autumn which helped project partners Knutson Construction and A&P Construction effectively launch their work, great strides have been made in all communities.

“Everyone at MDVA is excited to see such visible progress after so many years of advocacy, hard work and planning,” said Douglas Hughes, Deputy Commissioner - Healthcare. “Completion of these new Homes and the high-quality care they will provide will greatly benefit Veterans and their loved ones who have given so much in service to our country.”

These residential campuses will also bring new jobs to all three communities. While applications or resumes are not yet being accepted, you can learn more about employment opportunities by:

And, if you or someone you know has questions about living at any one of our new locations, please contact us at NewHomesAdmissions@state.mn.us.

What’s happening in Bemidji?

Bemidji will be home to a 72-bed facility located at 920 Anne Street N.W.

You can watch all of Bemidji’s construction progress through our onsite camera. Barring any unforeseen weather or supply chain challenges, we’ve set the following schedule for significant milestones between now and when the Home opens.

Anticipated Date Target
Spring 2022 Exterior walls will start to take shape, footings and foundations to be completed
Summer/Fall 2022 Roof structures, exterior finishes, heating/cooling systems installed, windows to be placed
Fall 2022/Winter 2023 Interior finishes, flooring, and small household appliances installed and tested
Spring 2023 Dietary/kitchen equipment, medical support equipment, furniture, landscaping/parking lot striping/walkways outdoor spaces be completed
Summer 2023 Commissioning, final walk throughs, and Residents accepted
Fall 2023 Grand opening celebration

What’s happening in Montevideo?

Montevideo will be home to a 72-bed facility located at 2190 William Avenue.

You can watch all of Montevideo’s construction progress through our onsite camera. Barring any unforeseen weather or supply chain challenges, we’ve set the following schedule for significant milestones between now and when the Home opens.

Anticipated Date Target
Spring 2022 Exterior walls will start to take shape, footings and foundations to be completed, and roof structures
Summer/Fall 2022 Slab on grade completed, interior framing, exterior finishes, heating/cooling systems installed, windows
Fall 2022/Winter 2023 Interior finishes, flooring, and small household appliances installed and tested
Spring 2023 Dietary/kitchen equipment, medical support equipment, furniture and landscaping, parking lot final coating, striping, walkways, outdoor spaces completed
Summer 2023 Building commissioning, final walk throughs, Residents accepted
Fall 2023 Grand opening celebration

What’s happening in Preston?

Preston will be home to a 54-bed facility located at 1112 Overlook Drive.

You can watch all of Preston’s construction progress through our onsite camera. Barring any unforeseen weather or supply chain challenges, we’ve set the following schedule for significant milestones between now and when the Home opens.

Anticipated Date Target
Spring 2022 Exterior walls will start to take shape, footings and foundations, roof framing and shingles
Summer/Fall 2022 Exterior finishes, heating/cooling systems installed, windows, curb and gutter, asphalt paving, landscaping
Fall 2022/Winter 2023 Interior finishes, flooring, and small household appliances installed and tested
Spring 2023 Dietary/kitchen equipment, medical support equipment and furniture to be installed
Summer 2023 Commissioning and final walk throughs and Residents accepted
Fall 2023 Grand opening celebration

Thank you for your ongoing support as we move forward in preparing to open these beautiful new State Veterans Homes in Bemidji, Montevideo and Preston.