This page contains all substantive, public administrative law decisions from the past seven years. To request a copy of an older decision, or a decision you believe should be public but cannot find on this page, please submit a data request. To view decisions regarding Municipal Boundary Adjustments, please visit the Boundary Adjustment Reporting System. 

25-2500-39971 In the Matter of the Application of Xcel Energy for a Certificate of Need for Additional Dry Cask Storage at the Prairie Island Nuclear Generating Plant Independent Spent Fuel Storage Installation

June 23, 2025 - It is recommended that the Minnesota Public Utilities Commission issue to Northern States Power Company d/b/a Xcel Energy a Certificate of Need for Additional Dry Cask Storage at the Prairie Island Nuclear Generating Plant Independent Spent Fuel Storage Installation in Goodhue County, with additional conditions.