This page contains all substantive, public administrative law decisions from the past seven years, and older decisions in rulemaking cases. To request a copy of an older decision, or a decision you believe should be public but cannot find on this page, please submit a data request. To view decisions regarding Municipal Boundary Adjustments, please visit the Boundary Adjustment Reporting System.
25-2500-40799 In the Matter of the Joint Application of Midwater BESS, LLC for a Site Permit and Route Permit for the up to 150 MW Midwater Energy Storage Project and Associated 161 kV Transmission Line in Freeborn County, Minnesota
May 13, 2026 - The Commission should DENY a Site Permit for the BESS Facility and DENY a Route Permit for the HVTL as discussed below.
Last Modified: 5/13/2026 Size: 0 Author: Categories: Tags: