Administrative Law Archives

This page contains all substantive, public administrative law decisions from the past seven years, and older decisions in rulemaking cases. To request a copy of an older decision, or a decision you believe should be public but cannot find on this page, please submit a data request. To view decisions regarding Municipal Boundary Adjustments, please visit the Boundary Adjustment Reporting System. 

25-2500-41066 In the Matter of Wisconsin Power & Light Company’s Site Permit Application for a Large Wind Energy Conversion System of up to 153 MW in Freeborn County, Minnesota

February 6, 2026 - Based upon these Conclusions, the Administrative Law Judge recommends that the Commission issue a Site Permit to WPL to construct and operate the Bent Tree North Project in Freeborn County, and that the Site Permit include the permit conditions as set forth above.

Last Modified: 2/6/2026 Size: 0 Author: Categories: Tags: