Interconnection Information
Whether you are planning to install solar yourself or work with a professional, there are several steps to take. First, you must gain approval from your local utility before you or anyone else installs any solar on your property. Most people work with a licensed, professional solar installer as the installation process can be complicated and must follow Minnesota laws and technical standards. The laws ensure safety, which includes making sure that utility systems are able to handle everyone who is generating their own energy. For help getting started with installing solar, check out the Clean Energy Resource Team for tips.
Minnesota law regulates statewide standards for the interconnection of distributed generation/distributed energy resources 10 MW and under which interconnect to the electric grid at the distribution level. The Commission and a Distributed Generation Work Group comprised of utilities, developers, and public stakeholders are in the process of updating these standards.
The current statewide standards do not cover projects larger than 10 MW or projects that interconnect directly to the transmission system. If a project is going to connect directly to the transmission grid, the Generation Interconnection Procedure at Midcontinent Independent Service Operator (MISO) applies.
See the following references for additional information on Minnesota’s Interconnection Process:
Minn. Stat. 216B.1611 : Interconnection of On-Site Distributed Generation.
MN DIP
[In Effect] Minnesota Distributed Energy Resource Interconnection Process and Agreement (MN DIP and DIA) as approved by the Commission’s April 19, 2019 Order. The following table lists the changes that have been made over time.
| Version | Date | Orders or Reason to Edit |
|
2.3 |
May 3, 2024 |
|
|
2.4 |
April 24, 2025 |
|
|
2.5 |
October 28, 2026 |
|
TIIR
[In effect] Minnesota Technical Interconnection and Interoperability Requirement (TIIR) as approved by the Commission's January 22, 2020 Order and updated per the Commission's April 27, 2020 Notice of Correction on the Interim Implementation Guidance for the TIIR developed by the Distributed Generation Workgroup's Technical Subgroup. The following table lists the changes that have been made over time.
| Version | Date | Orders or Reason to Edit |
|
2.0 |
April 11, 2023 |
|
|
2.1 |
January 1, 2026 |
|
|
2.2 |
October 28, 2026 |
|
Utility Interconnection Webpages
September 28, 2004 Order: Minnesota’s Statewide Interconnection Process and Technical Requirements . (Parts of these interconnection standards are still in effect. Attachment 6 on DG Rate Guidance is still in effect (Amended for the MN DIP by the October 10, 2023 Order listed above). Interim Implementation of the 2020 TIIR refers to Attachment 2.)
The Distributed Generation Workgroup offer updated templates for MN DIP Att. 2 Simplified Application Template (word version) and Att. 3 Interconnection Application (word version). These templates are optional for utilities’ use and do not change the MN DIP. (For more information or PDF versions, see the Commission’s May 7, 2021 Notice.)
Docket No. Year “16” – Number “521” : Updating Minnesota’s Statewide Interconnection Standards and Technical Requirements.
| Utility | Interconnection Webpage |
|
Dakota Electric |
dakotaelectric.com/renewable-energy/connect-your-own-system/ |
|
Minnesota Power |
|
|
Otter Tail Power |
otpco.com/help-center/how-to-connect-to-our-power-grid/minnesota-interconnection/ |
|
Xcel Energy |
