Skip to content

Odell Wind HVTL - 115 kV Transmission Line and Woad Hill Substation


Project Docket

Docket No 13-591
Project name Odell Wind HVTL - 115 kV Transmission Line and Woad Hill Substation
Applicant Geronimo Wind Energy, LLC; Odell Wind Farm, LLC
Description Odell Wind Farm, LLC is proposing to construct 9.5 miles of 115 kV transmission line to transmit energy generated at the planned 200 MW Odell Wind Farm to the Woad Hill Substation
Location Cottonwood County -- Mountain Lake Township, Jackson County -- Kimball Township, Martin County -- Cedar Township, Minnesota
Contact Richard Davis
richard.davis@state.mn.us
Status
  • 2014-01-23: Application accepted
  • 2014-02-10: Public meeting
  • 2014-04-14: Scoping decision
  • 2014-07-01: Environmental document available
  • 2014-07-09: Public hearing
  • 2014-10-29: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
eDockets 13-591

Key Project Documents

Date Title Description
10/29/2014 Commission Order and Route Permit Commission order granting a route permit to Odell Wind Farm, LLC for 115 kV Transmission Line and Woad Hill Substation
07/01/2014 Odell Wind HVTL - Environmental Assessment DOC-EERA has issued an Environmental Assessment (EA) on a 9.5 mile single circuit 115kV high voltage transmission line proposed by Odell Wind Farm, LLC in Cottonwood, Jackson and Martin counties

Project Documents