Kohlman Lake to Goose Lake 115 kV Transmission Line Project


Project Docket

Docket No E002/TL-12-1151
Project name Kohlman Lake to Goose Lake 115 kV Transmission Line Project
Applicant Northern States Power dba Xcel Energy
Description Xcel Energy proposes to replace an existing 115 kV transmission line with a new, double circuit 115 kV transmission line and to modify two existing substations in northeast Ramsey County
Location Ramsey County
Contact Ray Kirsch
raymond.kirsch@state.mn.us
651-539-1841
Status
  • 2013-03-15: Application accepted
  • 2013-04-23: Public meeting
  • 2013-06-26: Scoping decision
  • 2013-08-30: Environmental document available
  • 2013-09-10: Public hearing
  • 2014-01-21: Permit issued
  • 2015-04-20: Project built
  • 2015-05-20: Docket closed
eDockets 12-1151

Project Summary

Northern States Power Company (Xcel Energy) proposes to replace an existing 115 kilovolt (kV) transmission line with a new, double circuit 115 kV line, approximately 2.8 miles in length, in northeast Ramsey County.  The existing line and the proposed new, double circuit line pass through the cities of Maplewood, White Bear Lake, Vadnais Heights, and Gem Lake and through White Bear Township.  

The new double circuit 115 kV line will utilize single pole steel structures, approximately 80 to 90 feet in height.  The span between poles will be 300 to 500 feet.  Xcel Energy proposes to use the right-of-way of the existing 115 kV line to construct the new, double circuit 115 kV line.  If and where new right-of-way is required, the new right-of-way (easement) for the line will be 75 feet (37.5 feet on each side of the transmission line).

Xcel Energy's proposed project requires a route permit from the Minnesota Public Utilities Commission (Commission).  Department of Commerce, Energy Facility Permitting staff will conduct the environmental review for the project.  An administrative law judge from the Office of Administrative Hearings will hold a public hearing on the project. A decision by the Commission on a route permit is anticipated in September 2013.

Construction on the project is expected to begin after all permits are obtained, with an anticipated in-service date of summer 2015.

Key Project Documents

Date Title Description
01/21/2014 Route Permit for the Kohlman Lake to Goose Lake Project The route permit for the Kohlman Lake to Goose Lake 115 kV transmission line project, including route permit maps
08/30/2013 Environmental Assessment for the Kohlman Lake to Goose Lake Project Department of Commerce, Energy Facility Permitting staff has prepared and issued an environmental assessment (EA) for the Kohlman Lake to Goose Lake project. The EA identifies potential impacts and mitigation measures for the project
01/17/2013 Route Permit Application The route permit application submitted by Xcel Energy to the Minnesota Public Utilities Commission for the Kohlman Lake to Goose Lake 115 kV transmission line project