This opinion will be unpublished and
may not be cited except as provided by
Minn. Stat. § 480A.08, subd. 3 (2006).
STATE OF
IN COURT OF APPEALS
Southside Plumbing & Heating, Inc.,
Respondent,
vs.
Chris Plourde, et al.,
Appellants,
Western Bank, et al.,
Defendants.
Filed May 15, 2007
Hennepin County District Court
File No. 27-CV-05-013983
Julian C. Janes, Gislason, Martin & Varpness, P.A.,
Lawrence A. Wilford, Wilford & Geske,
William M. Hart, Karl J. Yeager, Melissa Dosick Riethof, Meagher & Geer, P.L.L.P., 33 South Sixth Street, Suite 4400, Minneapolis, MN 55402 (for respondent)
Considered and decided by Worke, Presiding Judge; Lansing, Judge; and Collins, Judge.[*]
U N P U B L I S H E D O P I N I O N
WORKE, Judge
On appeal in this mechanics’-lien attorney-fee dispute, appellants argue that the district court abused its discretion by awarding respondent attorney fees significantly in excess of the lien amount. We reverse and remand.
FACTS
In June 2004, appellant Chris Plourde (Plourde) purchased real property. Plourde hired a general contractor who hired respondent Southside Plumbing & Heating, Inc. On September 28, 2004, respondent sent Plourde a pre-lien notice by certified mail notifying him that if the general contractor did not pay respondent, it would file a claim against the property. Plourde received the notice and signed for its receipt.
Respondent did not receive full payment from the general contractor and served Plourde with a mechanics’-lien statement by certified mail on December 21, 2004. Plourde did not respond; thus, on September 21, 2005, respondent filed a complaint seeking a judgment that respondent is entitled to a mechanics’ lien on Plourde’s property in the amount of $1,251.33 plus interest, costs, disbursements, and attorney fees. Plourde failed to file an answer; instead, he wrote to respondent alleging that respondent failed to provide him with a pre-lien notice.
In November 2005, appellant Lehman Brothers Bank (Lehman Brothers), who recorded a mortgage against Plourde’s property on October 4, 2004, agreed to pay respondent $3,159.99, which included the lien amount and expenses. On December 6, 2005, Lehman Brothers issued a check to respondent, but revoked its settlement offer and stopped payment on the check two days later after Plourde objected to the payment.
On December 9, 2005, Plourde requested a copy of the pre-lien notice from respondent. Plourde also indicated that he would satisfy the lien in the amount of $1,251.33 pending proof of its validity. Respondent provided Plourde with a copy of the notice. On January 5, 2006, respondent rejected Plourde’s settlement offer, but indicated that it would settle for $4,000.
The next day, Plourde filed an answer admitting that respondent was entitled to recover $1,251.33 and indicating that the remaining issue was attorney fees. Respondent moved for summary judgment. On March 3, 2006, the district court held a hearing. The district court granted respondent’s motion and concluded that respondent’s attorney fees were incurred as a direct result of Plourde’s failure to act and Lehman Brothers’ breach of the settlement agreement. The district court ordered that respondent was entitled to a mechanics’ lien on Plourde’s property in the amount of $9,312.25—$1,251.33 for the lien amount, costs, $918.42 in disbursements, and $7,142.50 in attorney fees. This appeal follows.
D E C I S I O N
Appellants argue that the district
court abused its discretion in awarding attorney fees. In a mechanics’ lien foreclosure action, a
prevailing lienor is entitled to “costs and disbursements to be fixed by the
court.”
Appellants contend that attorney fees were not appropriate because
Plourde had no recollection of receiving the pre-lien notice and was well
within his rights to ask for a copy of the notice. “Whoever . . . contributes to the
improvement of real estate by performing labor, or furnishing skill, material
or machinery . . . shall have a lien upon the improvement, and upon the land on
which it is situated or to which it may be removed[.]”
Respondent sent Plourde the pre-lien notice by certified mail on September 28, 2004. Plourde signed for receipt of the notice. Plourde also admitted in his answer that respondent complied with the pre-lien notice filing provisions and was entitled to recoup the lien amount. Additionally, appellants acknowledge in their brief to this court that “[respondent] did serve upon Plourde a pre-lien notice in September 2004.” Although appellants argue that respondent should have provided Plourde with a copy of the pre-lien notice, respondent is not required to provide a copy of the notice. Because respondent complied with the requirement of providing Plourde with a pre-lien notice, the district court did not abuse its discretion in awarding respondent attorney fees.
Appellants argue that the district
court’s attorney-fees award was excessive.
Although the award of attorney fees is discretionary, the district court
should review (1) time and effort required, (2) novelty or difficulty of the
issues, (3) skill and standing of the attorney, (4) value of the interest
involved, (5) results secured at trial, (6) loss of opportunity for other
employment, (7) taxed party’s ability to pay, (8) customary charges for similar
services, and (9) certainty of payment. Jadwin v. Kasal, 318 N.W.2d 844, 848 (
Here, the district court ordered that respondent had a mechanics’ lien in the amount of $9,312.25, with the sum of $7,142.50 constituting attorney fees. The district court determined that respondent’s requested attorney fees were reasonable because Plourde’s memory loss regarding receipt of the notice did not mitigate the award of attorney fees; Plourde refused to pay attorney fees incurred even after he received a copy of the notice in December 2005; and Lehman Brothers breached their settlement agreement. The district court failed, however, to weigh the Jadwin factors. See 318 N.W.2d at 848. Most importantly, the district court failed to consider the legal work performed as it related to respondent’s motion for summary judgment.
In December 2005, Lehman Brothers agreed to pay respondent $3,159.99. One month later, after that offer was revoked, respondent demanded $4,000 for full settlement. Two months after that, the district court heard the summary-judgment motion. Thus, between the filing of the complaint on September 21, 2005, to the date of the settlement offer, respondent incurred less than $2,000 in attorney fees. And between the revocation of the settlement offer in December, to respondent’s demand one month later, respondent requested less than an additional $1,000 in attorney fees. Yet, between respondent’s demand for $4,000 and the summary-judgment hearing, held approximately two months later, respondent’s attorney fees increased to $7,142.50. The district court concluded that respondent requested attorney fees for: (1) preparing and filing the complaint, (2) serving appellants, (3) research and briefing issues, (4) appearing in court, and (5) communicating with appellants’ attorneys. Researching and briefing the issues and appearing in court were additional duties that respondent’s attorneys performed between the demand and the hearing date. The award for attorney fees is disproportionate to the interest being protected and is, therefore, unreasonable.
Reversed and remanded.
[*] Retired judge of the district court, serving as judge of the Minnesota Court of Appeals by appointment pursuant to Minn. Const. art. VI, § 10.