This opinion will be unpublished and
may not be cited except as provided by
Minn. Stat. § 480A.08, subd. 3 (2004).
STATE OF
IN COURT OF APPEALS
A05-795
petitioner,
Respondent,
vs.
Appellants.
Filed December 20, 2005
Reversed
Klaphake, Judge
Blue Earth County District Court
File No. C5-01-1506
Arvid Wendland, Wendland Law Office, P.O. Box 247, 825 East Second Street, Blue Earth, MN 56013; and
Considered and decided by Klaphake, Presiding Judge, Stoneburner, Judge, and Wright, Judge.
KLAPHAKE, Judge
Following
this court’s remand, the district court determined that respondent
On appeal, the Wingens argue that the district court overstated the county’s damages based on an incorrect assumption that the county would have been able to enter the Wingens’ property in September 2001, even though 90 days had not yet passed since the county filed its quick-take petition under Minn. Stat. § 117.042 (2000). The Wingens further argue that the damages claimed by the county were not suffered in consequence of the appeal as required by Minn. R. Civ. App. P. 108.01.
Because the burden was on the county to prove damages and because the county failed to prove which damages were incurred post-appeal, we reverse. The supersedeas bond is therefore discharged and the proceedings are dismissed.
The
district court initially awarded
On remand, the district court issued a number of findings, including the following:
2. The [county] had planned to acquire
fill from [the Wingens’] property for use on the CSAH 10 road reconstruction
project. However, as a result of the
appeal taken by [the Wingens], the [county’s] access to [the Wingens’] property
was temporarily curtailed. As the
project was already well underway at the time of the entry of the stay pending
appeal, [the county] determined to proceed with the project by acquiring
substitute fill [from
. . . .
6. As a direct consequence of [the Wingens’] appeals, [the county] needed to acquire 16,200 cubic yards of substitute fill from the Annis site. The cost of the fill itself, whether acquired from Annis or [the Wingens], was the same price and therefore can be disregarded. It is just the cost of transporting the fill that contributed to the damages.
7. The cost to transport the substitute fill from the Annis site was $4.86 per cubic yard for a total cost of $78,732. If [the Wingens] had not appealed, the cost of transporting the fill from their land would have been $2.85 per cubic yard or $46,170. Therefore, [the county] incurred an extra cost of $32,562 as a direct consequence of the appeal by [the Wingens].
Based on these findings, the district court concluded that the county suffered over $32,562 in damages “as a direct consequence of the appeal” filed by the Wingens.
While the Wingens’ current arguments on appeal are varied, a main theme emerges in the form of a challenge to the underlying assumption made by the district court that, but for the Wingens’ appeal and stay, the county was entitled to enter the Wingens’ property and take the fill it needed for the highway project. An examination of the record, however, establishes that the county decided to haul fill from the alternate Annis site well before the Wingens filed their October 9, 2001 appeal, and that the fill had been hauled from this alternate site before the Wingens’ appeal was perfected.
In particular, the record shows: (1) the county filed its quick-take petition seeking a temporary easement to take fill from the Wingens’ property on July 10, 2001; (2) on September 14, 2001, following a September 10 hearing at which the Wingens appeared pro se, the district court granted the quick-take petition and gave the county possession of the easement effective September 11; (3) on September 18, the Wingens’ newly retained attorney sent a letter to the county informing it of their intent to appeal, claiming that the county did not have the authority to enter their property and take fill until October 10, which was 90 days[1] after the county filed its quick-take petition, and warning the county not to enter the Wingens’ property; (4) on September 19, the county engineer, Alan Forsberg, entered into a contract to obtain fill from the alternate Annis site; and (5) the Wingens filed their appeal on October 9 and requested a stay, which was granted on October 22.
Thus, the evidence clearly shows that the county decided to obtain fill from an alternate location, the county entered into a binding contract to purchase that fill, and that most, if not all, of the fill had already been hauled by the time the Wingens filed their appeal. Because the county’s presentation on remand to the district court failed to distinguish between damages incurred pre-appeal and any that may have incurred after the Wingens filed their appeal, the county failed in its burden to prove the amount of damages incurred “as a consequence” of the Wingens’ appeal. We therefore reverse, order the bond discharged, and dismiss the proceedings.
Reversed.
[1] On appeal, the Wingens also argue that they
were not given the 90-day notice required by the quick-take statute, Minn.
Stat. § 117.042 (2000), and that the petition was not served by certified mail
as required by this statute. While the
Wingens have generally questioned whether the statutory quick-take provisions
were followed, the district court has not ruled on these issues and we decline
to address them further, particularly when this matter has been before this
court and the district court on several different occasions. See
Wingen II, 684 N.W.2d at 923 n.2 (noting that this court will refuse to
accept arguments pertaining to issues not presented to or decided by district
court, citing Thiele v. Stich, 425
N.W.2d 580, 582 (