Skip to content Loading

Project Search


Docket NumberProject NameDescriptionCreated Status
18-752Enbridge Energy, Limited Partnership has applied for a Pipeline Route Permit and Partial Exemption for the Fond du Lac Line 4 Project on the Fond du Lac Band of Lake Superior Chippewa Reservation. The Project will relocate approximately 10 miles of the existing Line 4 pipeline from the center to the outer edge of the existing Enbridge Mainline Corridor within the Fond du Lac Band Reservation. 03/04/2019 11:22 AM
  • 2019-02-25: Docket is open
  • 2019-04-11: Application accepted
  • 2019-05-22: Public meeting
  • 2019-06-28: ALJ report issued
  • : Permit Decision
  • : Project built
  • : Project Closed
16-685Great Plains seeks a Route Permit to construct an approximately 3- mile long, 8.625-inch-outside-diameter, high pressure natural gas transmission pipeline from its Fergus Falls Town Border Station (TBS) to its Green Plains Ethanol valve site in Otter Tail County10/31/2016 12:00 AM
  • Upcoming: Application accepted
  • Upcoming: Public meeting
  • Upcoming: Exemption granted
  • Upcoming: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
16-656Northern States Power Company (Xcel Energy) is proposing to construct an approximately 11,300 foot long, 16-inch outside-diameter, high pressure (650 psig) natural gas pipeline from the Northern Natural Gas Company Cedar Station in Eagan to Northern States Power Companys Black Dog Generating Plant in Burnsville, Minnesota08/18/2016 12:00 AM
  • Upcoming: Application accepted
  • Upcoming: Public meeting
  • Upcoming: Exemption granted
  • Upcoming: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
15-858Minnesota Energy Resources Corporation is proposing to install approximately 13.1 miles of new natural gas pipeline west and south of the city of Rochester in Olmsted County, Minnesota11/03/2015 12:00 AM
  • 2016-02-03: Application accepted
  • 2016-02-29: Public meeting
  • 2016-07-26: Routes accepted for consideration
  • 2016-09-16: Environmental document available
  • Upcoming: Public hearing
  • Upcoming: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
15-137Enbridge Energy proposes to replace 337 miles of the Line 3 Pipeline in Minnesota. Line 3 originates in Canada, continues through North Dakota, enters Minnesota in Kittson County, and terminates in Superior, Wiscsonsin. 02/23/2015 12:00 AM
  • 2015-07-01: Application accepted
  • 2016-04-25: Public meeting
  • 2016-12-05: Scoping decision
  • 2017-05-15: Draft EIS available
  • 2017-09-26: Public hearing
  • 2018-02-02: Final EIS available
  • 2018-04-24: ALJ report issued
  • 2018-10-26: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
14-320A Comparative Environmental Review of the Proposed Minnesota Pipe Line Reliability Project and the Alternatives Identified in the Certificate of Need Application08/29/2014 12:00 AM
  • 2014-08-29: Application accepted
  • 2015-02-06: Environmental document available
  • 2015-02-24: Public hearing
  • 2015-08-31: Certificate of Need issued
  • 2015-08-31: Project closed
  • Upcoming: Docket closed
13-978Minnesota Power is proposing to construct an approximate 5,900-foot-long, 10.75-inch-outside diamter, high pressure natural gas pipeline from a Northern Natural Gas pipeline to its Laskin Energy Center in Hoyt Lakes in St. Louis County11/05/2013 12:00 AM
  • 2013-12-20: Application accepted
  • 2014-01-22: Public meeting
  • 2014-05-12: Exemption granted
  • 2014-05-12: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed