Project Search


Docket NumberProject NameDescriptionCreated Status
17-308Dodge County Wind, LLC, proposes to construct approximately 25 miles of 345 kV high voltage transmission line in Dodge and Olmstead counties in Minnesota. 07/09/2018 12:42 PM
  • 2018-10-04: Application accepted
  • 2018-10-25: Public meeting
  • Upcoming: Scoping decision
17-701Blazing Star Wind Farm 2 is a 7.5 mile 115 kV Transmission Line planned for construction in Lincoln County04/25/2018 12:00 AM
  • 2018-05-23: Application accepted
  • 2018-06-12: Public meeting
  • Upcoming: Scoping decision
  • Upcoming: Environmental document available
  • Upcoming: Public hearing
  • Upcoming: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
17-185Xcel Energy and ITC Midwest LLC propose to construct a new 345 kilovolt (kV) transmission line from the Huntley substation near the towns of Huntley and Winnebago, Minnesota to the Wilmarth substation in the city of Mankato, Minnesota 12/12/2017 12:00 AM
  • 2018-03-28: Application accepted
  • 2018-04-17: Public meeting
  • 2018-07-17: Scoping decision
  • 2018-12-07: Draft EIS available
  • 2019-02-27: Public hearing
  • 2019-04-03: Final EIS available
  • Upcoming: ALJ report issued
  • Upcoming: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
17-322Freeborn Wind Energy LLC proposes to construct an approximately seven-mile long 161 kilovolt high voltage transmission line to interconnect the proposed Freeborn Wind Farm with the existing Glenworth Substation southeast of Glenville, Minnesota in Freeborn County09/13/2017 12:00 AM
  • 2017-12-05: Application accepted
  • 2017-12-19: Public meeting
  • 2018-03-07: Scoping decision
  • 2018-05-14: Environmental document available
  • 2018-05-31: Public hearing
  • 2018-09-20: Permit Decision
  • Upcoming: Project built
  • Upcoming: Docket closed
16-327Minnkota Power Cooperative proposes to build an approximately 9.4-mile 115 kilovolt high voltage transmission line and a new 115/4.16 kV distribution substation. This project, referred to as the MPL-Laporte 115 kV Transmission Line Project, will serve an industrial load for a new pumping station to be constructed and operated by Minnesota Pipeline Company, LLC04/25/2016 12:00 AM
15-423Great River Energy proposes to construct approximately 13 miles of new 115 kilovolt transmission line and a new 115 kV breaker station, in Aitkin County, northeast of the city of Aitkin07/29/2015 12:00 AM
  • 2015-10-19: Application accepted
  • 2015-10-27: Public meeting
  • 2015-12-23: Scoping decision
  • 2016-04-20: Environmental document available
  • 2016-05-05: Public hearing
  • Upcoming: Permit Decision
  • Upcoming: Project built
  • Upcoming: Docket closed
15-628Great River Energy proposes to construct approximately 2.5 miles of new 115 kV electric transmission line near the city of Backus in Cass County07/24/2015 12:00 AM
  • 2015-09-17: Application accepted
  • 2015-10-12: Public meeting
  • 2015-12-10: Scoping decision
  • 2016-03-03: Environmental document available
  • 2016-03-30: Public hearing
  • Upcoming: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
15-204Great River Energy (GRE) and Minnesota Power (MP) are proposing to construct the Motley Area 115 kV Project, a 115 kilovolt (kV) high voltage transmission line (HVTL) and associated facilities near the city of Motley in Morrison, Cass and Todd counties. 03/27/2015 12:00 AM
  • 2015-04-30: Application accepted
  • 2015-05-19: Public meeting
  • 2015-07-14: Scoping decision
  • 2015-11-16: Environmental document available
  • 2015-11-19: Public hearing
  • 2015-12-29: ALJ report issued
  • 2016-03-23: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
15-33North Star Solar PV, LLC is filing a Joint Application for a 100 MW solar generating plant site permit and connecting 115 kV transmission line route permit in Chisago County01/29/2015 12:00 AM
  • 2015-04-27: Application accepted
  • 2015-04-30: Public meeting
  • 2015-06-24: Scoping decision
  • 2015-09-24: Environmental document available
  • 2015-10-07: Public hearing
  • 2016-02-16: Permit issued
  • 2016-04-06: Permit Amended
  • 2016-12-08: Project built
  • Upcoming: Docket closed
14-977Minnesota Power's proposed 16 Line Reroute project is an approximately three-mile-long 115 kilovolt HVTL located in St. Louis County, Minnesota01/22/2015 12:00 AM
  • 2015-02-26: Application accepted
  • 2015-03-23: Public meeting
  • 2015-05-19: Scoping decision
  • 2015-10-05: Environmental document available
  • 2015-10-27: Public hearing
  • 2016-01-22: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
14-797Great River Energy and Minnesota Power propose to construct a new 115 kV transmission line and to construct and modify substations near the city of Menahga in Hubbard, Wadena, and Becker County09/25/2014 12:00 AM
  • 2015-03-18: Application accepted
  • 2015-03-24: Public meeting
  • 2015-05-26: Scoping decision
  • 2015-09-28: Environmental document available
  • 2015-10-19: Public hearing
  • 2015-11-18: ALJ report issued
  • 2016-03-14: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
14-665Minnkota Power is planning a new 115 kV transmission line and new 115/4.16 substation in Clearwater County08/06/2014 12:00 AM
  • 2016-01-25: Application accepted
  • 2016-02-22: Public meeting
  • 2016-06-30: Scoping decision
  • 2016-09-13: Application withdrawn
  • Upcoming: Docket closed
14-21Minnesota Power, in partnership with Manitoba Hydro, proposes to construct a 500 kV high voltage transmission line (HVTL) from the International border that would terminate at the Blackberry Substation in Itasca County04/15/2014 12:00 AM
13-591Odell Wind Farm, LLC is proposing to construct 9.5 miles of 115 kV transmission line to transmit energy generated at the planned 200 MW Odell Wind Farm to the Woad Hill Substation12/12/2013 12:00 AM
  • 2014-01-23: Application accepted
  • 2014-02-10: Public meeting
  • 2014-04-14: Scoping decision
  • 2014-07-01: Environmental document available
  • 2014-07-09: Public hearing
  • 2014-10-29: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
12-1163Minnesota Power hereby applies to the Minnesota Public Utilities Commission for a Certificate of Need to construct the Great Northern Transmission Line10/21/2013 12:00 AM
  • 2014-01-08: Application accepted
  • 2014-02-20: Public meeting
  • 2014-04-22: Scoping decision
  • 2014-07-11: Environmental document available
  • 2014-12-03: Public hearing
  • 2015-03-16: ALJ report issued
  • Upcoming: Certificate of Need issued
  • Upcoming: Docket closed
13-68Minnesota Power proposes to construct approximately one mile of new 115 kV transmission line, approximately 0.3 miles of new 230 kV transmission line, and a replacement substation east of the city of Deer River in Itasca County. The Deer River Transmission Project would also rebuild approximately 0.9 miles of an existing 115 kV transmission line, and remove approximately 7.5 miles of existing 115 kV transmission line04/16/2013 12:00 AM
  • 2013-06-19: Public meeting
  • 2013-06-27: Application accepted
  • 2013-08-08: Scoping decision
  • 2013-11-20: Environmental document available
  • 2014-01-06: Public hearing
  • 2014-06-10: Permit Decision
  • 2015-12-14: Project built
  • Upcoming: Project closed
12-1337ITC Midwest, LLC (ITCM) proposes to construct a new 345 kV transmission line in Jackson, Martin, and Faribault County; to reroute several existing 161 kV lines; and to construct a new substation near the cities of Winnebago and Blue Earth. 01/24/2013 12:00 AM
  • 2013-06-27: Application accepted
  • 2013-07-16: Public meeting
  • 2013-10-14: Scoping decision
  • 2014-03-21: Draft EIS available
  • 2014-05-13: Public hearing
  • 2014-07-11: Final EIS available
  • 2014-09-08: ALJ report issued
  • 2014-11-25: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
12-1245Great River Energy proposes to rebuild a portion of the existing 69 kV transmission system and construct a new double-circuit 115 kV transmission line in Scott and Rice counties11/16/2012 12:00 AM
  • 2013-09-09: Application accepted
  • 2013-10-01: Public meeting
  • 2013-11-27: Scoping decision
  • 2014-02-21: Environmental document available
  • 2014-03-04: Public hearing
  • 2014-08-05: Certificate of Need issued
  • 2014-08-05: Permit issued
  • 2016-08-25: Project built
  • Upcoming: Docket closed
12-401Xcel Energy proposes to upgrade the Chaska Area 69 kV transmission line to 115 kV capacity in in eastern Carver County and northern Scott County near and within the City of Chaska, and through Laketown, Dahlgren, and Jackson townships 07/11/2012 12:00 AM
  • 2012-09-12: Application accepted
  • 2012-09-26: Public meeting
  • 2012-11-19: Scoping decision
  • 2013-03-25: Environmental document available
  • 2013-05-02: Public hearing
  • 2013-10-15: Permit issued
  • 2015-09-09: Project built
  • Upcoming: Docket closed
11-948Xcel Energy proposes to upgrade the Scott-County-Bluff Creek-Westgate 69 kV transmission line to 115 kV capacity near the cities of Chanhassen, Shorewood, Excelsior, Deephaven, Greenwood, Minnetonka and Eden Prairie, 02/24/2012 12:00 AM
  • 2012-05-24: Application accepted
  • 2012-07-18: Public meeting
  • 2012-08-14: Scoping decision
  • 2012-10-30: Scoping decision
  • 2013-02-25: Environmental document available
  • 2013-05-16: Public hearing
  • 2014-01-23: Permit issued
  • 2016-11-15: Project built
  • Upcoming: Docket closed
09-1448Xcel Energy Application to construct a new 345 kV and a new 161kV transmission line from the Hampton Substation, through Rochester, to a proposed substation in La Crosse, Wis01/07/2010 12:00 AM
  • 2010-03-09: Application accepted
  • 2010-05-04: Public meeting
  • 2010-08-06: Scoping decision
  • 2011-03-21: Draft EIS available
  • 2011-06-14: Public hearing
  • 2011-08-31: Final EIS available
  • 2012-05-30: Permit issued
  • 2016-09-12: Project built
  • Upcoming: Docket closed
02-44A utility seeking a route permit for a transmission line that meets certain qualifications may elect to seek approval from a local unit of government. If local review is elected, a permit from the Public Utilities Commission is not required. This docket contains local review projects05/27/2003 12:00 AM
01-30Annual Hearing for the Power Plant Siting and Transmission Line Routing Program02/01/2002 12:00 AM