Menahga Area 115 kV Transmission Line Project


Project Docket

Docket No ET2, E015/TL-14-797
Project Name Menahga Area 115 kV Transmission Line Project
Applicant Great River Energy; Minnesota Power
Description Great River Energy and Minnesota Power propose to construct a new 115 kV transmission line and to construct and modify substations near the city of Menahga in Hubbard, Wadena, and Becker County
Location Becker County, Hubbard County, Wadena County
Contact Ray Kirsch
raymond.kirsch@state.mn.us
651-539-1841
Status
  • 2015-03-18: Application accepted
  • 2015-03-24: Public meeting
  • 2015-05-26: Scoping decision
  • 2015-09-28: Environmental document available
  • 2015-10-19: Public hearing
  • 2015-11-18: ALJ report issued
  • 2016-03-14: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
eDockets 14-797

Project Summary

Great River Energy and Minnesota Power (applicants) have proposed to construct approximately 22.5 miles of new 115 kV transmission line in the counties of Becker, Hubbard, and Wadena.  The project includes the construction of three new substations and the modification of two existing substations. 

The applicants indicate that the new 115 kV transmission line poles will range in height from 60 to 90 feet, with a span between poles of 275 to 400 feet.  The applicants have requested a 100 foot right-of-way (easement) for the transmission line (50 feet on each side of the transmission line centerline). 

The proposed project requires two approvals from the Minnesota Public Utilities Commission (Commission) before it may be constructed -- a certificate of need (CN) and a route permit.  The applicants filed a joint CN and route permit application with the Commission in January 2015.   

Department of Commerce, Energy Environmental Review and Analysis staff prepared an environmental assessment for the project.  An administrative law judge from the Office of Administrative Hearings held a public hearing.  Upon completion of the environmental review and hearing process, the Commission issued a certificate of need and route permit for the project on March 14, 2016.

The applicants began construction of the project in spring 2016; the project was energized in May 2017.

This project docket page includes information on the route permitting process, but also includes, as appropriate, information related to the CN process.  Additional information on the CN process can be found on the eDockets website: CN-14-787.  

Key Project Documents

Date Title Description
03/14/2016 Route Permit for the Menahga Area 115 kV Project The route permit issued by the Commission for the Menahga Area 115 kV transmission line project. Includes route permit text and maps
03/14/2016 Commission Order Issuing a Certificate of Need and Route Permit for the Menahga Area 115 kV Project Commission order issuing a certificate of need and route permit. Includes the Commission's order, findings of fact, route permit, and maps
09/28/2015 Environmental Assessment for Menahga Area 115 kV Project The environmental assessment (EA) evaluates the potential human and environmental impacts of the project and possible mitigation measures, including route and site alternatives. The EA also evaluates alternatives to the project itself
01/15/2015 Menahga Area 115 kV Joint Certificate of Need and Route Permit Application The certificate of need and route permit application submitted by Great River Energy and Minnesota Power for the Menahga Area 115 kV transmission line project

Project Documents