This webpage contains information and documents related to the permitting of this project by the Minnesota Public Utilities Commission. Every project before the Commission has an electronic docket (eDocket), a file folder for all of the project's documents.

Documents for this project are listed below in the File Register, most recent documents first. To view the eDockets record for this project, click on the eDockets link below, or click on the eDockets tab in the File Register. A subset of the record, including key documents with descriptions, is available by clicking on the Energy Facilities tab in the File Register.

For more information about participating in the permitting of this project, click on the How to Participate tab, or contact the environmental review manager or public advisor listed below.

Project Docket

Docket No E015/TL-13-805
Project name HVTL Route Permit Application - Minnesota Canisteo Project
Applicant Minnesota Power
Description Minnesota Power proposes to construct two, approximately five-mile, 115 kV HVTLs and a substation near Coleraine, Minnesota. The two transmission lines, each 5.2 miles in length, would be constructed parallel to one another with an overlapping ROW of 160 feet.
Subjects Environmental policy; Electric power transmission; HVTL
Location St. Louis County
Docket created: October 09, 2013
Contacts: Bill Storm, 651-539-1844, Environmental Review Manager.
Status:
 
12-17-2013
Public meeting
 
02-5-2014
Scoping decision
 
04-4-2014
Environmental document available
 
04-15-2014
Public hearing
 
07-2-2014
Permit issued
 
11-12-2014
Project built
 
Docket closed
eDockets 13-805
Mailing list Contact the Public Utilies Commission at docketing.puc@state.mn.us or 651-201-2204 or 1-800-657-3782 to sign up.
Project Summary

Minnesota Power proposes to construct two, approximately five-mile, 115 kV HVTLs and a substation near Coleraine, Minnesota.  The two transmission lines, each 5.2 miles in length, would be constructed parallel to one another with an overlapping ROW of 160 feet.  The key components of the proposed project include:

  • The proposed HVTLs would connect to Minnesota Power’s existing 28 Line west of Scenic Highway 7, traverse south across Reilly Beach Road to the Canisteo Pit, and then turn southwest where they would terminate at the proposed Canisteo Substation.
  • The new Canisteo Substation would be constructed north of County Highway 61 and east of County Road 325 near the western edge of the Canisteo Pit.


 

File Register
Energy Facilities eDockets
DateDocumentDescription
07/02/14 HVTL Route Permit - Minnesota Power Canisteo Transmission Line Project | document details
On July 2, 2014, the Minnesota Public Utilities Commission issued a HVTL Route Permit, including a description of the route and other conditions of the permit and the official maps of the route, to Minnesota Power in accordance with Minn. Stat. 216E
04/04/14 Notice of Environmnetal Assessment Availability - MP Canisteo HVTL Project | document details
PLEASE TAKE NOTICE that the Minnesota Department of Commerce, Energy Environmental Review and Analysis (EERA) announces the release of the environmental assessment (EA) for the proposed MP Canisteo HVTL project
04/04/14 Environmental Assessment - Minnesota Power Proposed Canisteo HVTL Project
This environmental assessment (EA) addresses the issues noted in Minnesota Rule 7850.3700, subpart 4, and those identified in the Department’s scoping decision for this project
03/31/14 Notice of Public Hearing for the Canisteo HVTL Project | document details
A hearing will be held on April 15, 2014, at 1:00 p.m. at the Bovey City Hall on Minnesota Power's Application to the PUC for a HVTL Route Permit for the Canisteo HVTL project in Itasca County. Public comments will be accepted by the administrative law judge through May 14, 2014
02/05/14 Scoping Decision: Minnesota Power's Proposed Canisteo HVTL Project | document details
The Deputy Commissioner, Department of Commerce has issued a decision on the scope of the Environmental Assessment to be prepared for Minnesota Power's proposed Canisteo HVTL project
01/03/14 Public Comments on the Scope of the Environmental Review Document
The EERA held a Public Scoping meeting on the MP Canisteo HVTL project on December 18, 2013; the comment period allowing the public to submit comments on the scope of the EA was open until January 3, 2014. The following comments were received
12/17/13 PUC Order HVTL Route Permit Application Completeness - MP Canisteo HVTL Project | document details
On December 17, 2013, the Commission accepted the RP application submitted by Minnesota Power for the MP Canisteo HVTL project
12/04/13 Notice: Public Information and Environmental Review Scoping Meeting, MP Canisteo HVTL Project | document details
The PUC and DOC EERA will conduct public information and environmental review scoping meetings on December 18, 2013, at the Bovey City Hall. Comments will be accepted until January 3, 2014
12/02/13 Draft Scoping Document MP Canisteo HVTL Project | document details
This draft scoping document is intended to advise the public of the scoping process and the process for the preparation of the Environmental Review document. The Scoping Decision will identify for the public the issues and alternatives that the Department of Commerce (DOC) has determined are appropriate for inclusion in the environmental review document
10/28/13 Department of Commerce - Energy Environmental Review and Analysis Comments and Recommendations MP Canisteo RPA | document details
The Minnesota Department of Commerce (DOC) Energy Environmental Review and Analysis (EERA) staff is providing the Commission with Comments and Recommendations on the completeness of the route permit application, possible contested issues of fact and appointment of an advisory task force for the Canisteo RPA docket
10/09/13 HVTL Route Permit Application - Minnesota Power's Canisteo Project
Minnesota Power (MP) submitted an application to the Minnesota Public Utilities Commission for a HVTL Route Permit under the alternative permitting process for the proposed relocation of MP Canisteo HVTL project
09/06/13 Minnesota Power's 10-day Notification Letter | document details
Minnesota Power hereby notifies the Minnesota Public Utilities Commission of its intent to submit an Application for a Route Permit for the Canisteo Project pursuant to the alternative permitting procedures in Minn. Rules 7850.2800 to 7850.3900 and the statutory timeframe set forth in Minn. Stat. § 216E.04, subd. 7