Documents for this project are listed below in the File Register, most recent documents first. To view the eDockets record for this project, click on the eDockets link below, or click on the eDockets tab in the File Register. A subset of the record, including key documents with descriptions, is available by clicking on the Energy Facilities tab in the File Register.

For more information about participating in the permitting of this project, click on the How to Participate tab, or contact the environmental review manager or public advisor listed below.

Project Docket

Docket No IP-6855/WS-11-608
Project name Ellerth Windpark
Applicant TCI Renewables
Description Ellerth Wind, LLC site permit application for the 98.9 MW for the Ellerth Windpark in Marshall County
Subjects Environmental policy; Wind power
Location Marshall County; Marshall County -- Newfolden City; Comstock, Foldahl, Marsh Grove,Viking, West Valley and Wright Townships
Docket created: October 20, 2011
Contacts: Larry Hartman, 651-539-1839, Environmental Review Manager.
Status:
 
12-7-2011
Application accepted
 
Draft permit issued
 
Public meeting
 
Permit issued
 
Project built
 
Docket closed
eDockets 11-608
Mailing list • Register (if you have never established an account) Or
• Sign on (if you already have established an account for other mailing lists)
Project Summary

File Register
Energy Facilities eDockets
DateDocumentDescription
06/08/12 Notice of Availability of Environmental Report for Ellerth Windpark Project | document details
Notice of Availability of Environmental Report for Commission's Certificate of Need Proceeding for the Ellerth Windpark Project in Marshall County
06/08/12 Environmental Report for 98.9 MW Ellerth Windpark Project Certificate of Need Application (5.04 MB) | document details
Energy Facility Permitting has released an Environmental Report for the the Project for the Commission's Certificate of Need Review (CN-11-112)
12/29/11 Public and Agency Comments on ER Scope for the Ellerth Windpark Project | document details
Comments received through the end of the November 30, 2011, Environmental Report scoping comment period (CN-11-112)
12/29/11 Environmental Report Scoping Decision for 98.9 MW Ellerth Windpark Project Certificate of Need Application | document details
The Department of Commerce has released the Environmental Report Scoping Decision for the Project for the Commisison's Certificate of Need Review (CN-11-112)
12/28/11 Public Meeting Presentation Material for Ellerth Windpark Project ER Scoping Meeting | document details
Presentation material from the November 7, 2011, public meeting concerning the certificate of need (CN-11-112) environmental report and wind site perming processes
12/28/11 Public Comments from ER Scoping Meeting for Ellerth Windpark Project | document details
Comments received at the public information and scoping meeting on November 7, 2011, in Newfolden
12/08/11 Notice of Application Acceptance and Comment Period | document details
Comments on the Completeness of the Ellerth Wind LLC Site Permit Application will be accepted until 4:30 p.m. on January 13, 2012
11/22/11 DOC EFP comments and recommendations on application acceptance for the Ellerth Windpark in Marshall County | document details
Comments and Recommendations to the Commission recommending acceptance of the site permit application of Ellerth Wind LLC for the 98.9 MW Ellerth Windpark in Marshall County
11/03/11 Site Permit Application for Ellerth Windpark
Site permit application for the Ellerth Windpark; refiled November 3, 2011
10/24/11 Notice of Information and Scoping Meeting for Ellerth Windpark | document details
The Department of Commerce will conduct a public information and environmental report scoping meeting at the Newfolden Community Center on November 7, 2011, on the proposed Ellerth Windpark in Marshall County. Comments are accepted until November 30, 2011
05/27/11 Certificate of Need Application for Ellerth Windpark in Marshall County | document details
Application for Certificate of Need by Ellerth Wind, LLC in Docket No. 11-112