Documents for this project are listed below in the File Register, most recent documents first. To view the eDockets record for this project, click on the eDockets link below, or click on the eDockets tab in the File Register. A subset of the record, including key documents with descriptions, is available by clicking on the Energy Facilities tab in the File Register.

For more information about participating in the permitting of this project, click on the How to Participate tab, or contact the environmental review manager or public advisor listed below.

Project Docket

Docket No E002/TL-11-152
Project name Hollydale 115 kV Transmission Line Project in the Cities of Plymouth and Medina, Hennepin County
Applicant Xcel Energy
Description Xcel Energy and Great River Energy (GRE) propose removing approximately eight miles of an existing GRE-owned 69 kilovolt (kV) overhead transmission line and constructing a new 115 kV overhead transmission in its place, constructing an additional eight-tenths of a mile of new 115 kV overhead transmission line, constructing a new substation, and modifying associated transmission facilities in the cities of Medina and Plymouth, Hennepin County, Minnesota
Subjects Environmental policy; Electric power transmission
Location Hennepin County; Twin Cities Metropolitan Area
Docket created: June 30, 2011
Contacts: Ray Kirsch, 651-539-1841, Environmental Review Manager.
Status:
 
08-25-2011
Application accepted
 
10-26-2011
Public meeting
 
07-31-2012
Scoping decision
 
Environmental document available
 
Public hearing
 
Permit issued
 
Project built
 
Docket closed
eDockets 11-152
Mailing list • Register (if you have never established an account) Or
• Sign on (if you already have established an account for other mailing lists)
Project Summary

On June 30, 2011, Xcel Energy and Great River Energy submitted an application to the Minnesota Public Utilities Commission (Commission) for a route permit to construct the proposed Hollydale 115 kV transmission line. The project entails removing approximately eight miles of an existing GRE-owned 69 kilovolt (kV) overhead transmission line and constructing a new 115 kV overhead transmission in its place, constructing an additional eight-tenths of a mile of new 115 kV overhead transmission line, constructing a new substation, and modifying associated transmission facilities in the cities of Medina and Plymouth in Hennepin County.

On August 25, 2011, the Commission accepted the application and authorized review under the alternative permitting process, pursuant to Minnesota Statutes Chapter 216E (Power Plant Siting Act) and Minnesota Rules 7850.2800 to 7850.3900.

As authorized by the Commission, an advisory task force (ATF) was established. The ATF was charged with, (1) identifying specific impacts and issues of local concern, and (2) identifying potential alternative transmission line routes or route segments and alignments that may maximize positive impacts and/or minimize or avoid negative impacts of the project. The ATF met two times in October and November 2011. The recommendations of the ATF can be found in its final report.

A public information and scoping meeting was held by the Department of Commerce on October 26, 2011, at the Best Western Kelly Inn in Plymouth, Minnesota. Comments on the scope of the environmental assessment were accepted until November 9, 2011. The scoping decision document was completed and made available on December 7, 2011.

On February 27, 2012, the applicants filed a petition requesting that the Commission convert the pending route permit proceeding for the proposed Hollydale 115 kV transmission line project from the alternative permitting process to the full permitting process.

On May 4, 2012, the Commission issued an Order granting a request by the applicants to convert the pending Hollydale 115 kV transmission line route permit proceeding from the alternative permitting process to the full permitting process, pursuant to The Power Plant Siting Act and Minnesota Rules 7850.1700 to 7850.2700. As a result, the environmental review document for the project will now be an environmental impact statement (EIS).

The full permitting process is a one year process that generally commences on the date that the Commission accepts the route permit application as complete. With the Hollydale project, however, the Commission ordered the full process on May 4, 2012.

Additional public information meetings were held on June 7 and 8, 2012, at Wayzata High School in Plymouth, Minnesota. The meetings were presided over by administrative law judge, Eric L. Lipman with the Minnesota Office of Administrative Hearings. The meetings were an opportunity for members of the public to learn about the proposed project and provide comment on the scope of the EIS that will be prepared by Department of Commerce. Approximately 270 persons attended the public hearing on June 7, 2012, and 90 persons attended the afternoon hearing on June 8, 2012.

Department of Commerce Energy Facility Permitting staff anticipates that the Draft EIS will be released in fall 2012.

To receive future notices of meetings and document availability please sign up for the mailing list. Documents for this project are available below and on the eDockets website by clicking the following link: Route Permit Application - Hollydale 115 kV Transmission Line Project (E002/TL-11-152).

Certificate of Need

A Certificate of Need (CN) Notice Plan Petition and CN Request for Exemption Petition for this project was filed by the applicants on February 3, 2012. A separate but related docket (ET2/CN-12-113) pertaining to the CN has been opened and documents are available for review on the Department of Commerce eDockets webpage. For more information on the CN docket please click on the following link: Certificate of Need Docket - Hollydale 115 kV Transmission Line Project (ET2/CN-12-113).

File Register
Energy Facilities eDockets
DateDocumentDescription
07/31/12 EIS Scoping Decision for the Hollydale 115 kV Transmission Line Project (3.2 MB) | document details
The scoping decision describes those issues and alternative routes which will be evaluated in the environmental impact statement (EIS) for the Hollydale 115 kV transmission line project. The EIS is expected to be completed and available in September 2012
07/27/12 Comments on the Scope of the Hollydale EIS
Comments on the scope of the environmental impact statement for the proposed Hollydale 115 kV transmission line project. Recorded at public meetings on June 7 and 8, 2012, and received by administrative law judge Eric L. Lipman through the public comment period of June 22, 2012
05/25/12 Draft EIS Scoping Document (3.4 MB) | document details
This draft scoping document is intended to advise the public of the scoping process and the process for the preparation of the EIS
05/24/12 Notice of Public Information Meetings for the Hollydale 115 kV transmission line project (38 KB) | document details
Public information meetings will be held for the Hollydale 115 kV transmission line on Thursday, June 7, 2012, from 6-9 p.m. and Friday, June 8, 2012, from 1-4 p.m. at Wayzata High School in Plymouth. Public comments on the scope of the environmental impact statement will be accepted until June 22, 2012
05/04/12 Commission Notice and Order for a Hearing Under Minnesota Rules Chapter 1405 (140 KB) | document details
Commission order granting conversion of the Hollydale project to the full permitting process and referring the docket to the Office of Administrative Hearings for a contested case proceeding
02/27/12 Xcel Energy and Great River Energy Petition to Convert (672 KB) | document details
Xcel Energy and Great River Energy are requesting that the Commission convert the pending route permit proceeding for the proposed Hollydale 115 kV transmission line project from the alternative permitting process to the full permitting process
12/07/11 Scoping Decision for the Hollydale 115 kV Transmission Line Rebuild Project Environmental Assessment (2.8 MB) | document details
The scoping decision describes those issues and alternative routes which will be evaluated in the environmental assessment for the Hollydale 115 kV project. The environmental assessment is expected to be completed and available in February 2012
11/28/11 Comments on scope of Hollydale environmental assessment
Comments received at the public information and scoping meeting and through the end of comment period of November 9, 2011, on the scope of the environmental assessment for the proposed Hollydale 115 kV rebuild project
10/27/11 Meeting Presentation and Handouts
The presentation and handouts available for the public meeting on October 26, 2011 in Plymouth, Minn
10/13/11 Notice of Hollydale Transmission Project Advisory Task Force Meetings (54 KB) | document details
Task force meetings will be held at the Best Western Kelly Inn, 2705 North Annapolis Lane, Plymouth, Minnesota. Meetings are open to the public but participation is limited to task force members
10/12/11 Notice of Public Information and Scoping Meeting for the Hollydale 115 kV transmission line project (1.6 MB) | document details
The Department of Commerce will hold a public information and scoping meeting on the proposed Hollydale 115 kV transmission line project on October 26, 2011. Public comments on the scope of the environmental assessment will be accepted until November 9, 2011
09/15/11 Hollydale Advisory Task Force Information Page
The Public Utilities Commission authorized the Department of Commerce to structure and charge an advisory task force for the proposed Hollydale 115 kV transmission line project to review issues and route alternatives for the environmental assessment
08/25/11 Public Utilities Commission Order on application acceptance for the Xcel-GRE Hollydale 115kV transmission line project (1.4 MB) | document details
PUC order accepting the application for a high-voltage route permit for the Hollydale 115kV transmission line project as complete under the alternative review process
08/16/11 EFP Comments and Recommendations on the Hollydale 115 kV Route Permit Application (1.4 MB) | document details
Staff recommendations that the Commission accept the route permit application as complete under the Alternative Review Process of the Power Plant Siting Act
06/30/11 Route Permit Application
Xcel Energy's and Great River Energy's application for proposed Hollydale 115 kV Transmission Line Project in the cities of Plymouth and Medina, Hennepin County, under the alternative permitting process