This webpage contains information and documents related to the permitting of this project by the Minnesota Public Utilities Commission. Every project before the Commission has an electronic docket - an eDocket, a file folder for all of the project.s documents.
Documents for this project are listed below in the File Register, most recent documents first. To view the eDockets record for this project, click on the eDockets link below, or click on the eDockets tab in the File Register. A subset of the record, including key documents with descriptions, is available by clicking on the Energy Facilities tab in the File Register.
For more information about participating in the permitting of this project, click on the How to Participate tab, or contact the state permit manager or public advisor listed below.
Application accepted |
Public meeting |
Scoping decision |
Draft EIS available |
Public hearing |
Final EIS available |
Permit Decision |
Permit Amended |
Permit Amended |
Xcel Energy and Great River Energy are making this Application to construct a new 345 kV high voltage transmission line (HVTL) between the Red River, either at a location south of Moorhead or south of Breckenridge, and the new Quarry Substation west of St. Cloud.
The Minnesota portion of the proposed Fargo to St. Cloud 345 kV Project will be approximately 169 to 180 miles long, extending from the Red River to the existing Alexandria Switching Station located south of Alexandria and to the new Quarry Substation to be located west of St. Cloud. The North Dakota portion of the Project from a new Bison Substation west of Fargo to the Red River, depending on the route selected, will be approximately 31 to 81 miles.
The proposed structures will primarily include single-pole, double-circuit capable, self-weathering or galvanized steel structures that will range in height between 130 and 175 feet. The span length between structures will range between 600 and 1,000 feet depending on site-specific considerations. Although the proposed line will be built using double-circuit capable poles, only one circuit will be installed for this Project. The second position will be left available for a future additional circuit, as per the Commission’s Certificate of Need (CN) Order. The right-of-way for the proposed 345 kV electrical transmission line will generally be 150 feet in width.
Construction of the Project is expected to begin in 2014 and be completed and in service by the second quarter of 2015.
(On May 22, 2009, the Commission issued an Order granting a Certificate of Need (CN) for the CapX 2020 projects. The CN record can be reviewed by entering year "06" and number "1115" at https://www.edockets.state.mn.us/EFiling/search.jsp . OES environmental analysis for the CN record can be viewed at http://mn.gov/commerce/energyfacilities/Docket.html?Id=19120.)
| Primary Documents | ||
| Date | Document | Description |
| Route Permit for the Fargo to St. Cloud 345 kV Transmission Line | document details | The Commission has issued an Order granting a Route Permit to Xcel Energy and Great River Energy, including a description of the route and other conditions of the permit and links to the official maps of the route |
|
| Date | Document | Description |
| Application for Approval of Minor Alterations to the Fargo-St. Cloud 345 kV Transmission Line Rourt Permit | Xcel Energy and Great River Energy have requested approval of a Minor Alteration to the Route Permit in Otter Tail and Grant counties |
|
| Permit Amendment for a Route Alteration | document details | The Commission has approved an alteration and issued a Route Permit Amendment to the 345 kV Fargo-St. Cloud Route Permit issued on June 24, 2011 |
|
| EFP Comments and Recommendations on a Minor Ateration for the Fargo-St. Cloud 345 KV Transmission Line | document details | EFP has submitted comments to the Commission concerning the Request for a Minor Alteration in Oak Township, Stearns County |
|
| Notice of Minor Alteration Request for the Fargo-St. Cloud 345 kV Transmission Line | document details | A comment period is open through February 3, 2012 for the Xcel Energy/Great River Energy request to alter the route permit in Oak Township in Stearns County |
|
| Permit Amendment for Route Alterations (9.12 M) | document details | The Commission has approved 10 alterations and issued a Route Permit Amendment to the 345 kV Fargo-St. Cloud Route Permit issued on June 24, 2011 |
|
| Application for Approval of Minor Alteration to the Fargo-St. Cloud 345 kV Transmission Line Rourt Permit (1.22 M) | document details | Xcel Energy and Great River Energy have requested approval of a Minor Alteration to the Route Permit in Oak Township in Stearns County |
|
| EFP Comments and Recommendations on a Permit Amendment for the Fargo-St. Cloud 345 KV Transmission Line | document details | EFP has submitted comments to the Commission concerning the Route Permit Amendment provision and in particular eleven requested adjustments southeast of Alexandria |
|
| Notice of Request for Permit Amendments for Fargo-St. Cloud 345 kV Transmission Line Project | document details | The Permittees have requested a number of amendments to the permit for the segment between Alexandria and St. Cloud. A public comment period on the requests is open through October 14, 2011 |
|
| Permit Amendment Requests for the Fargo-St. Cloud 345 kV Transmission Line | The Permittees have requested a number of amendments to the permit for the segment between The Alexandria Switch and the Quarry Substation in St. Joseph |
|
| Route Permit for the Fargo to St. Cloud 345 kV Transmission Line | document details | The Commission has issued an Order granting a Route Permit to Xcel Energy and Great River Energy, including a description of the route and other conditions of the permit and links to the official maps of the route |
|
| EFP Supplemental Comments & Recommendations on the Route Permit for the Fargo to St. Cloud 345 kV Transmission Line | document details | EFP staff has supplemented its original Comments and Recommendations identifying revisions to enhance or clarify the original filing |
|
| EFP Comments & Recommendations on the Route Permit for the Fargo to St. Cloud 345 kV Transmission Line | EFP has submitted Comments, Findiings of Fact, Conclusions and a proposed Order to the Commission for issuing a Route Permit to Xcel Energy and Great River Energy for the Project |
|
| Letter from the Commission on Next Steps in Fargo-St. Cloud Route Permit Process | document details | The Commission has issued a notice explaining the final process going forward following the release of the ALJ Report |
|
| ALJ Findings of Fact, Conclusions and Recommendation (6.18 M) | document details | The Administrative Law Judge has filed her findings of fact, conclusions of law and a route recommendation in the Fargo-St. Cloud CapX 2020 project |
|
| Final Environmental Impact Statement for Fargo to St. Cloud 345 kV Transmission Project | OES has released the Final EIS for the Project. Documents and maps are available through this link |
|
| Notice of Availability of the Final Environmental Impact Statement for Fargo to St. Cloud 345 kV Transmission Line Project | document details | OES has released the Final EIS responding to timely substantive comments received on the Draft EIS. The Draft and Final serve as the complete EIS for the proposed project |
|
| Notice of Public Hearing for Fargo to St. Cloud 345 kV Transmission Line Project | document details | A public hearing is being convened along the route from November 16, 2010, to December 2, 2010, at the times and places listed in this notice. A comment period will be open through January 5, 2011. (See the notice for instruction on how to send comments to the ALJ.) |
|
| Notice of Availability of Draft EIS and Public Information Meetings for Fargo to St. Cloud 345 kV Transmission Line Project | document details | OES has released the Draft Environmental Impact Statement for the Project. Public Meetings will be held at the times and places in this notice to take public comment on the DEIS. A public comment period will remain open through October 18, 2010 |
|
| Draft EIS for the Fargo-St. Cloud 345 kV Transmission Project | OES has released the Draft Environmental Impact Statement for the Project. Documents and maps are available through this link |
|
| Notice to Landowners along Scoping Amendment Route Additions | document details | Notice sent (along with Scoping Decision Amendment and Maps) to landowners along alternate routes being evaluated in the draft EIS for the Fargo to St. Cloud 345 kV transmission project |
|
| Amendment to the EIS Scoping Decision for the Fargo to St. Cloud 345 kV Transmission Project | document details | The OES Director has amended his Scope determining the impacts and alternative routes to be evaluated in the Environmental Impact Statement. The amendment includes additional route options to be considered in the EIS (1.97 M, .pdf) |
|
| Administrative Law Judge's Prehearing Order | document details | The ALJ has filed this Prehearing Order setting forth the dates and procedures relevant to the contested case hearing for the Fargo to St. Cloud 345 kV Project (409.92K, .pdf) |
|
| Notice to Landowners along Route Alternatives | document details | Notice and maps sent to landowners along alternate routes being evaluated in the draft EIS for the Fargo to St. Cloud 345 kV transmission project (6.51 M, .pdf) |
|
| Comments on the Scope of the Environmental Impact Statement for the Fargo to St. Cloud 345 kV Transmission Line | Comments received at the public information and scoping meetings and through the end of comment period of February 12, 2010 |
|
| OES Director's Scoping Decision on the Fargo-St. Cloud Project EIS | document details | The Office of Energy Security Director has issued his Scope determining the impacts and alternative routes to be evaluated in the Environmental Impact Statement for the Fargo-St. Cloud 345 kV Transmission Project |
|
| Freeport to St. Cloud Advisory Task Force Information Page Updated with Final Report | The PUC authorized OES to structure and charge an advisory task force for the Fargo to St. Cloud 345 kV transmission line project to review issues and route alternatives for the Environmental Impact Statement |
|
| Public Meeting Materials for the Fargo to Monticello 345 kV HVTL Public EIS Scoping Meetings | OES has provided presentation and informational materials to attendees at the public meetings. These same materials are also available here |
|
| Notice of Public Information and EIS Scoping Meetings | document details | OES is conducting public meetings along the proposed Fargo to St. Cloud 345 kV Transmission Line Project. The public is invited to attend to gather information and share comments on the project and potential alignment alternatives. A comment period on the scope of the Environmental Impact Statement is open through February 12, 2009 |
|
| OES Comments and Recommendations on Application Acceptance | document details | OES recommends to the Commission to accept the application as complete and to authorize OES to name a Public Advisor and establish an Advisory Task Force |
|
| Application to the Minnesota Public Utilities Commission for a Route Permit | Application for a route permit for the Fargo to St. Cloud 345 kV Transmission Line Project |
|
| Date | Document | On Behalf Of | Description |
| 06/17/13 | 20136-88231-02 | XCEL ENERGY | COMPLIANCE FILING--COMPLAINT RESOLUTION SPREADSHEET_FARGO-SC 4-15 TO 5-31-13 |
| 06/17/13 | 20136-88231-01 | XCEL ENERGY | COMPLIANCE FILING--FARGO TO ST CLOUD COMPLAINT REPORT JUNE 2013 |
| 06/17/13 | 20136-88237-01 | PUC | PUBLIC COMMENT |
| 06/06/13 | 20136-87903-01 | PUC | NOTICE OF COMMENT PERIOD--ON MINOR ALTERATION APPLICATION |
| 06/06/13 | 20136-87903-02 | PUC | NOTICE OF COMMENT PERIOD--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 06/05/13 | 20136-87861-01 | PUC | LETTER--TO WILLIAM P. LUTHER RE APPLICATION FOR A ROUTE PERMIT |
| 06/03/13 | 20135-87685-01 | NORTHERN STATES POWER COMPANY | OTHER--TABLES TO MINOR ALTERATION REQUESTS FILED MAY 23, 2013 |
| 05/28/13 | 20135-87468-05 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 4 OF 5 FOR PLAN AND PROFILE ALEX TO BORDER SEGMENT 4 |
| 05/28/13 | 20135-87468-07 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENTS 2 THROUGH 4 TO PLAN AND PROFILE ALEX TO BORDER SEGMENT 4 |
| 05/28/13 | 20135-87468-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--FILING LETTER FOR PLAN AND PROFILE - ALEX TO BORDER - SEGMENT 4 |
| 05/28/13 | 20135-87468-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 1 OF 5 FOR PLAN AND PROFILE ALEX TO BORDER SEGMENT 4 |
| 05/28/13 | 20135-87468-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 3 OF 5 FOR PLAN AND PROFILE ALEX TO BORDER SEGMENT 4 |
| 05/28/13 | 20135-87468-06 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 5 OF 5 FOR PLAN AND PROFILE ALEX TO BORDER SEGMENT 4 |
| 05/28/13 | 20135-87468-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 2 OF 5 FOR PLAN AND PROFILE ALEX TO BORDER SEGMENT 4 |
| 05/24/13 | 20135-87430-01 | LUTHER CENTURY FARM, LLC | OTHER--REQUEST TO APPROVE APPLICATION |
| 05/23/13 | 20135-87295-03 | NORTHERN STATES POWER COMPANY, A MINNESOTA CORPORATION, AND GREAT RIVER ENERGY, A MINNESOTA COOPERATIVE CORPORATION | OTHER--ATTACHMENT D PART 1, PART 3 OF 4 |
| 05/23/13 | 20135-87295-01 | NORTHERN STATES POWER COMPANY, A MINNESOTA CORPORATION, AND GREAT RIVER ENERGY, A MINNESOTA COOPERATIVE CORPORATION | OTHER--APPLICATION FOR APPROVAL OF FOUR MINOR ALTERATIONS, PART 1 OF 4 |
| 05/23/13 | 20135-87295-02 | NORTHERN STATES POWER COMPANY, A MINNESOTA CORPORATION, AND GREAT RIVER ENERGY, A MINNESOTA COOPERATIVE CORPORATION | OTHER--ATTACHMENTS A, B, AND C, PART 2 OF 4 |
| 05/23/13 | 20135-87295-04 | NORTHERN STATES POWER COMPANY, A MINNESOTA CORPORATION, AND GREAT RIVER ENERGY, A MINNESOTA COOPERATIVE CORPORATION | OTHER--ATTACHMENT D PART 2, PART 4 OF 4 |
| 05/10/13 | 20135-86878-01 | XCEL ENERGY | COMPLIANCE FILING |
| 04/19/13 | 20134-85902-01 | XCEL ENERGY | COMPLIANCE FILING--COMPLAINT REPORT - 2/15/13 -- 4/15/13 |
| 04/15/13 | 20134-85731-01 | XCEL ENERGY | COMPLIANCE FILING |
| 02/15/13 | 20132-83889-01 | XCEL ENERGY | COMPLIANCE FILING--1/15/13 -- 2/15/13 COMPLAINT REPORT |
| 02/15/13 | 20132-83877-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--POLE NOS 569 TO 588 AND 604 TO 772 SIGNED PLAN AND PROFILE |
| 02/13/13 | 20132-83802-01 | PUC | LETTER--TO DARIN LAHR RE APPLICATION FOR A ROUTE PERMIT |
| 02/13/13 | 20132-83802-02 | PUC | LETTER--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 02/08/13 | 20132-83669-01 | DOC EFP | COMPLIANCE REVIEW--PLAN AND PROFILE |
| 02/06/13 | 20132-83613-01 | XCEL ENERGY | COMPLIANCE FILING |
| 02/06/13 | 20132-83602-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--MNDOT PERMITS FOR ALEXANDRIA TO BORDER |
| 01/25/13 | 20131-83201-06 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENTS 3 AND 4 FOR PLAN AND PROFILE ALEX TO BORDER SEGMENTS 7-9 |
| 01/25/13 | 20131-83201-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 2 OF 2 FOR PLAN AND PROFILE ALEX TO BORDER SEGMENTS 7-9 |
| 01/25/13 | 20131-83201-05 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 2 PART 2 OF 2 FOR PLAN AND PROFILE ALEX TO BORDER SEGMENTS 7-9 |
| 01/25/13 | 20131-83201-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--FILING LETTER FOR PLAN AND PROFILE - ALEX TO BORDER - SEGMENTS 7-9 |
| 01/25/13 | 20131-83201-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 2 PART 1 OF 2 FOR PLAN AND PROFILE ALEX TO BORDER SEGMENTS 7-9 |
| 01/25/13 | 20131-83201-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 1 OF 2 FOR PLAN AND PROFILE ALEX TO BORDER SEGMENTS 7-9 |
| 01/18/13 | 20131-82926-01 | XCEL ENERGY | COMPLIANCE FILING--COMPLAINT REPORT SUMMARY, 12/15/12--1/15/13 |
| 01/15/13 | 20131-82765-01 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL FARGO TO ST. CLOUD FILING LTR TO HAAR ENC MNDOT EXCEPTION REQUEST |
| 01/10/13 | 20131-82596-01 | XCEL ENERGY | COMPLIANCE FILING |
| 12/19/12 | 201212-81979-01 | XCEL ENERGY | COMPLIANCE FILING |
| 12/19/12 | 201212-81991-01 | XCEL ENERGY | COMPLIANCE FILING--ALSO IN DOCKET 09-246 |
| 12/04/12 | 201212-81357-56 | PUC | NOTICE--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 12/04/12 | 201212-81357-28 | PUC | NOTICE--POWER PLANT SITING AND TRANSMISSION LINE ROUTING PROGRAM ANNUAL HEARING |
| 12/03/12 | 201212-81318-01 | PUC | PUBLIC COMMENT--PC OUTSIDE OF OPEN COMMENT PERIOD |
| 11/28/12 | 201211-81120-01 | XCEL ENERGY | COMPLIANCE FILING |
| 11/15/12 | 201211-80690-01 | XCEL ENERGY | COMPLIANCE FILING--COMPLAINT REPORT FOR 10/15/12 -- 11/15/12. |
| 11/02/12 | 201211-80318-01 | PUC | LETTER--TO DARIN LAHR RE REVIEW OF PLAN AND PROFILE COMPLIANCE FILING |
| 11/02/12 | 201211-80318-02 | PUC | LETTER--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 10/24/12 | 201210-79842-01 | XCEL ENERGY | COMPLIANCE FILING |
| 10/15/12 | 201210-79577-01 | XCEL ENERGY | COMPLIANCE FILING |
| 10/09/12 | 201210-79388-01 | DOC EFP | COMPLIANCE FILING--RESPONSE TO PLAN AND PROFILE FILING |
| 10/03/12 | 201210-79191-02 | PUC | LETTER--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 10/03/12 | 201210-79191-01 | PUC | LETTER--TO DARRIN LAHR AND CAROLE SCHMIDT RE ROUTE PERMIT APPLICATION FOR THE FARGO-ST. CLOUD 345 KV TRANSMISSION LINE PROJECT |
| 09/28/12 | 20129-79011-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--FILING LETTER AND ALEXANDRIA TO BORDER SEGMENT 3 PNP ATTACHMENTS 2 TO 4 |
| 09/28/12 | 20129-79011-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ALEXANDRIA TO BORDER SEGMENT 3 PNP ATTACHMENT 1 PART 2 |
| 09/28/12 | 20129-79011-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ALEXANDRIA TO BORDER SEGMENT 3 PNP ATTACHMENT 1 PART 1 |
| 09/28/12 | 20129-79011-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ALEXANDRIA TO BRODER SEGMENT 3 PNP ATTACHMENT 1 PART 3 |
| 09/27/12 | 20129-79009-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--REVISION TO SEGMENT 5B PLAN AND PROFILE |
| 09/24/12 | 20129-78910-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--FINAL CECP |
| 09/18/12 | 20129-78763-02 | PUC | LETTER--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 09/18/12 | 20129-78763-01 | PUC | LETTER--TO DARRIN F. LAHR RE REVIEW OF COMPLIANCE FILING - ALIGNMENT CHANGE FOR STRUCTURES 362-364 |
| 09/17/12 | 20129-78705-01 | XCEL ENERGY | COMPLIANCE FILING--COVER |
| 09/17/12 | 20129-78705-02 | XCEL ENERGY | COMPLIANCE FILING--REPORT |
| 09/13/12 | 20129-78634-01 | DOC EFP | COMPLIANCE FILING--RESPONSE TO FILING ON ALIGNMENT CHANGE |
| 09/10/12 | 20129-78489-01 | DOC EFP | NOTICE--STATE REGISTER NOTICE OF PERMIT |
| 09/06/12 | 20129-78423-01 | RICHARD AND MARY LOU WANDERSCHEID | LETTER--NOTICE OF RESOLUTION OF COMPLAINT |
| 08/31/12 | 20128-78312-01 | PUC | PUBLIC COMMENT--OUTSIDE OF OPEN COMMENT PERIOD |
| 08/20/12 | 20128-77988-01 | XCEL ENERGY | COMPLIANCE FILING |
| 08/17/12 | 20128-77957-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE POLE NOS 362 TO 364 MODIFIED ALIGNMENT |
| 08/15/12 | 20128-77887-01 | XCEL ENERGY | COMPLIANCE FILING--COMPLAINT REPORT |
| 08/03/12 | 20128-77566-01 | DOC EFP | COMPLIANCE FILING--RESPONSE TO ENVIRONMENTAL CONTROL PLAN |
| 07/27/12 | 20127-77326-01 | MINNESOTA DEPARTMENT OF NATURAL RESOURCES | COMMENTS |
| 07/20/12 | 20127-77012-01 | PUC | LETTER |
| 07/20/12 | 20127-76990-01 | DOC EFP | COMPLIANCE FILING--ACKNOWLEDGEMENT OF RECEIPT - COMPLAINT REPORTING |
| 07/17/12 | 20127-76847-01 | XCEL ENERGY | COMPLIANCE FILING--XCEL FARGO ST. CLOUD COMPLAINT REPORT |
| 07/10/12 | 20127-76653-01 | DOC EFP | COMPLIANCE FILING--RESPONSE TO 2B AND 5B PLAN AND PROFILE FILING |
| 07/06/12 | 20127-76547-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENT 5B ATTACHMENT 2 PART 4 |
| 07/06/12 | 20127-76547-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENT 5B ATTACHMENT 2 PART 3 |
| 07/06/12 | 20127-76547-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--FILING LETTER FOR PNP SEGMENT 5B ATTACHMENT 2 PARTS 3 AND 4 |
| 06/28/12 | 20126-76166-07 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 722 TO 752 |
| 06/28/12 | 20126-76166-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 527C TO 569 |
| 06/28/12 | 20126-76166-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 570 TO 609A |
| 06/28/12 | 20126-76166-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 493B TO 527B |
| 06/28/12 | 20126-76161-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX C LAYDOWN YARDS |
| 06/28/12 | 20126-76161-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 274 TO 313 |
| 06/28/12 | 20126-76166-06 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 687A TO 721 |
| 06/28/12 | 20126-76162-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 314 TO 347 |
| 06/28/12 | 20126-76161-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 226 TO 273 |
| 06/28/12 | 20126-76162-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 415A TO 454 |
| 06/28/12 | 20126-76162-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 381 TO 415 |
| 06/28/12 | 20126-76166-05 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 651 TO 687 |
| 06/28/12 | 20126-76162-05 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 454A TO 493A |
| 06/28/12 | 20126-76161-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 179 TO 225 |
| 06/28/12 | 20126-76166-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 610 TO 650 |
| 06/28/12 | 20126-76166-08 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX E THROUGH APPENDIX J |
| 06/28/12 | 20126-76162-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX D POLES 348 TO 380 |
| 06/27/12 | 20126-76159-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX B MAPBOOK PART 1 OF 2 |
| 06/27/12 | 20126-76076-10 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENTS 2B AND 5B ATTACHMENT 5 PART 3 |
| 06/27/12 | 20126-76157-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--APPENDIX B AVIAN MITIGATION PLAN MAPS 25 47 PART 2 OF 4 |
| 06/27/12 | 20126-76076-09 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENTS 2B AND 5B ATTACHMENT 5 PART 2 |
| 06/27/12 | 20126-76076-07 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENTS 2B AND 5B ATTACHMENT 4 |
| 06/27/12 | 20126-76157-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--FILING LETTER AND CECP TOC ITEMS 1 TO 5 |
| 06/27/12 | 20126-76157-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--APPENDIX B AVIAN MITIGATION PLAN MAPS 1 24 PART 1 OF 4 |
| 06/27/12 | 20126-76076-06 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENTS 2B AND 5B ATTACHMENT 3 |
| 06/27/12 | 20126-76076-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENTS 2B AND 5B ATTACHMENT 1 PART 3 |
| 06/27/12 | 20126-76076-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--FILING LETTER FOR PNP SEGMENTS 2B AND 5B AND ATTACHMENT 1 PART 1 |
| 06/27/12 | 20126-76157-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--CECP SWPPP CAPX2020 ALEXANDRIA TO ND BORDER AND APPENDIX A |
| 06/27/12 | 20126-76157-06 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--APPENDIX B AVIAN MITIGATION PLAN MAPS 62 93 PART 4 OF 4 |
| 06/27/12 | 20126-76159-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SWPPP APPENDIX B MAPBOOK PART 2 OF 2 |
| 06/27/12 | 20126-76076-05 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENTS 2B AND 5B ATTACHMENT 2 PART 2 |
| 06/27/12 | 20126-76076-08 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENTS 2B AND 5B ATTACHMENT 5 PART 1 |
| 06/27/12 | 20126-76157-05 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--APPENDIX B AVIAN MITIGATION PLAN MAPS 48 61 PART 3 OF 4 |
| 06/27/12 | 20126-76076-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENTS 2B AND 5B ATTACHMENT 2 PART 1 |
| 06/27/12 | 20126-76076-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PNP SEGMENTS 2B AND 5B ATTACHMENT 1 PART 2 |
| 06/26/12 | 20126-76027-01 | RICHARD AND MARY LOU WANDERSCHEID | LETTER--COMPLAINT |
| 06/18/12 | 20126-75724-01 | DOC EFP | COMPLIANCE FILING--ACKNOWLEDGEMENT OF RECEIPT-MONTHLY COMPLAINT REPORTS |
| 06/14/12 | 20126-75629-01 | XCEL ENERGY | COMPLIANCE FILING--COMPLAINT REPORT |
| 06/01/12 | 20126-75303-02 | PUC | LETTER--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 06/01/12 | 20126-75303-01 | PUC | LETTER--TO DARRIN LAHR AND TIMOTHY LISSON - REVIEW OF COMPLIANCE FILING - PLAN AND PROFILE - SEGMENT 5A AND 6 |
| 05/21/12 | 20125-74862-01 | DOC EFP | COMPLIANCE FILING--REVIEW OF PLAN AND PROFILE |
| 05/21/12 | 20125-74859-01 | DOC EFP | COMPLIANCE FILING--ACKNOWLEDGEMENT OF RECEIPT |
| 05/17/12 | 20125-74820-04 | PUC | MINUTES--MARCH 8, 2012 AGENDA MEETING |
| 05/15/12 | 20125-74746-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--CAPX ROUTE PERMIT COMPLAINT SUMMARY REPORT |
| 05/09/12 | 20125-74563-01 | PUC | LETTER--REVIEW OF COMPLIANCE FILING - ALEXANDRIA SWITCHING STATION |
| 05/09/12 | 20125-74568-01 | PUC | LETTER--REVIEW OF COMPLIANCE FILING - ALEXANDRIA SWITCHING STATION WITH SIGNATURE |
| 05/09/12 | 20125-74568-02 | PUC | LETTER--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 05/04/12 | 20125-74454-01 | DOC EFP | COMPLIANCE FILING--DOC EFP REVIEW OF PLAN AND PROFILE |
| 05/03/12 | 20125-74441-08 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 5 APPENDIX D PART 2 TO CAPX 2020 PLAN AND PROFILE SEGMENTS 5A AND 6 |
| 05/03/12 | 20125-74452-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--SUPPLEMENT EDOCKET SUMISSIOMN NO. 20124-73793-01, FILED 4-9-12 |
| 05/03/12 | 20125-74441-06 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 5 APPENDIX B TO CAPX 2020 PLAN AND PROFILE SEGMENTS 5A AND 6 |
| 05/03/12 | 20125-74441-04 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 3 TO CAPX 2020 PLAN AND PROFILE SEGMENTS 5A AND 6 |
| 05/03/12 | 20125-74441-02 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 TO CAPX 2020 PLAN AND PROFILE SEGMENTS 5A AND 6 |
| 05/03/12 | 20125-74441-09 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 5 APPENDIX D PART 3 TO CAPX 2020 PLAN AND PROFILE SEGMENTS 5A AND 6 |
| 05/03/12 | 20125-74441-07 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 5 APPENDIX D PART 1 TO CAPX 2020 PLAN AND PROFILE SEGMENTS 5A AND 6 |
| 05/03/12 | 20125-74441-05 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 4 TO CAPX 2020 PLAN AND PROFILE SEGMENTS 5A AND 6 |
| 05/03/12 | 20125-74441-01 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | COMPLIANCE FILING--LETTER FOR CAPX 2020 PLAN AND PROFILE SEGMENTS 5A AND 6 |
| 05/03/12 | 20125-74441-03 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 2 TO CAPX 2020 PLAN AND PROFILE SEGMENTS 5A AND 6 |
| 04/25/12 | 20124-73979-01 | PUC | LETTER--TO DARRIN LAHR AND TIMOTHY LISSON RE REVIEW OF COMPLIANCE FILING |
| 04/20/12 | 20124-73849-01 | DOC EFP | COMPLIANCE FILING--ACKNOWLEDGEMENT OF RECEIPT OF COMPLAINT FILING |
| 04/20/12 | 20124-73828-01 | DOC EFP | COMPLIANCE FILING--DOC EFP REVIEW OF PLAN AND PROFILE |
| 04/19/12 | 20124-73793-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING |
| 04/17/12 | 20124-73673-01 | XCEL ENERGY | COMPLIANCE FILING--RESPONSE TO COUNTY ROAD 2 COMPLAINT LETTERS |
| 04/16/12 | 20124-73634-01 | XCEL ENERGY | COMPLIANCE FILING--COVER |
| 04/16/12 | 20124-73634-02 | XCEL ENERGY | COMPLIANCE FILING--REPORT |
| 04/12/12 | 20124-73540-01 | PUC | ORDER--APPROVING MINOR ALTERATIONS AND ISSUING A ROUTE PERMIT AMENDMENT |
| 04/12/12 | 20124-73540-02 | PUC | ORDER--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 04/05/12 | 20124-73365-06 | PUC | MINUTES--FEBRUARY 16, 2012 AGENDA MEETING |
| 04/02/12 | 20124-73226-07 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4. ATTACHMENT 1. PART 6 OF 7 |
| 04/02/12 | 20124-73226-09 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4. ATTACHMENT 2 |
| 04/02/12 | 20124-73226-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--FILING LETTER FOR PLAN AND PROFILE SEGMENTS 3 AND 4 |
| 04/02/12 | 20124-73228-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4 .ATTACHMENT 3. PART 2 OF 5 |
| 04/02/12 | 20124-73226-06 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4 .ATTACHMENT 1 .PART 5 OF 7 |
| 04/02/12 | 20124-73226-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4 .ATTACHMENT 1 .PART 2 OF 7 |
| 04/02/12 | 20124-73226-10 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4 .ATTACHMENT 3. PART 1 OF 5 |
| 04/02/12 | 20124-73228-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4 .ATTACHMENT 3. PART 5 OF 5 |
| 04/02/12 | 20124-73228-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4. ATTACHMENT 3. PART 3 OF 5 |
| 04/02/12 | 20124-73226-05 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4 .ATTACHMENT 1. PART 4 OF 7 |
| 04/02/12 | 20124-73226-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4. ATTACHMENT 1. PART 3 OF 7 |
| 04/02/12 | 20124-73226-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4. ATTACHMENT 1 .PART 1 OF 7 |
| 04/02/12 | 20124-73228-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4 .ATTACHMENT 3 .PART 4 OF 5 |
| 04/02/12 | 20124-73226-08 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE SEGMENTS 3 AND 4. ATTACHMENT 1. PART 7 OF 7 |
| 03/29/12 | 20123-73114-01 | DOC EFP | COMPLIANCE FILING--ACKNOWLEDGEMENT OF RECEIPT OF ADDITIONAL PLAN AND PROFILE INFORMATION FOR POLES 111-116 |
| 03/27/12 | 20123-73030-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--FILING LETTER AND MNDOT UTILITY PERMIT AGREEMENT |
| 03/23/12 | 20123-72870-01 | DOC EFP | COMPLIANCE FILING--ACKNOWLEDGEMENT OF RECEIPT OF FINAL ECP FOR ALEXANDRIA TO ST. CLOUD |
| 03/23/12 | 20123-72868-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--POLE NO 111 TO 116 PLAN AND PROFILE ATTACHMENT 2 PART 3 OF 3 |
| 03/23/12 | 20123-72868-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--POLE NO 111 TO 116 PLAN AND PROFILE ATTACHMENT 2 PART 1 OF 3 |
| 03/23/12 | 20123-72868-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--POLE NO 111 TO 116 PLAN AND PROFILE ATTACHMENT 2 PART 2 OF 3 |
| 03/23/12 | 20123-72868-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--POLE NO 111 TO 116 PLAN AND PROFILE FILING LETTER AND ATTACHMENT 1 |
| 03/23/12 | 20123-72886-01 | SCOTT AND BELINDA WALSH | LETTER |
| 03/23/12 | 20123-72868-05 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--POLE NO 111 TO 116 PLAN AND PROFILE ATTACHMENT 3 |
| 03/19/12 | 20123-72728-01 | DOC EFP | COMPLIANCE FILING--ACKNOWLEDGEMENT OF RECEIPT OF COMPLAINT FILING |
| 03/15/12 | 20123-72620-01 | XCEL ENERGY | COMPLIANCE FILING |
| 03/07/12 | 20123-72314-01 | XCEL ENERGY | COMPLIANCE FILING--FILING LETTER FOR ALEXANDRIA TO ST CLOUD CONSTRUCTION ENVIRONMENTAL CONTROL PLAN |
| 03/07/12 | 20123-72314-03 | XCEL ENERGY | COMPLIANCE FILING--CECP AVIAN MITIGATION PLAN AND APPENDIX A |
| 03/07/12 | 20123-72314-07 | XCEL ENERGY | COMPLIANCE FILING--CECP AVIAN MITIGATION PLAN APPENDIX B PART 4 OF 4 |
| 03/07/12 | 20123-72314-09 | XCEL ENERGY | COMPLIANCE FILING--CECP STORMWATER POLLUTION PREVENTION PLAN APPENDICES D TO J |
| 03/07/12 | 20123-72314-06 | XCEL ENERGY | COMPLIANCE FILING--CECP AVIAN MITIGATION PLAN APPENDIX B PART 3 OF 4 |
| 03/07/12 | 20123-72314-04 | XCEL ENERGY | COMPLIANCE FILING--CECP AVIAN MITIGATION PLAN APPENDIX B PART 1 OF 4 |
| 03/07/12 | 20123-72314-02 | XCEL ENERGY | COMPLIANCE FILING--INTRODUCTION TO CONSTRUCTION ENVIRONMENTAL CONTROL PLAN |
| 03/07/12 | 20123-72314-05 | XCEL ENERGY | COMPLIANCE FILING--CECP AVIAN MITIGATION PLAN APPENDIX B PART 2 OF 4 |
| 03/07/12 | 20123-72314-08 | XCEL ENERGY | COMPLIANCE FILING--CECP STORMWATER POLLUTION PREVENTION PLAN APPENDICES A TO C |
| 02/29/12 | 20122-72024-01 | DOC EFP | BRIEFING PAPERS--COMMENTS AND RECOMMENDATIONS ON A MINOR ALTERATION |
| 02/24/12 | 20122-71839-13 | PUC | NOTICE OF COMMISSION MEETING--MARCH 8, 2012 |
| 02/23/12 | 20122-71817-01 | PUC | ORDER--ORDER DENYING RECONSIDERATION |
| 02/23/12 | 20122-71817-02 | PUC | ORDER--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 02/21/12 | 20122-71762-01 | DOC EFP | COMPLIANCE CLOSURE--ACKNOWLEDGEMENT OF RECEIPT |
| 02/15/12 | 20122-71608-01 | XCEL ENERGY | COMPLIANCE FILING |
| 02/15/12 | 20122-71580-01 | PUC | LETTER--TO DARRIN LAHR AND TIMOTHY LISSON - COMMISSION REVIEW OF COMPLIANCE FILING |
| 02/13/12 | 20122-71485-01 | DOC EFP | COMPLIANCE FILING--RECOMMENDATION TO COMMISSION ON PLAN AND PROFILE SEGMENT 2A |
| 02/10/12 | 20122-71430-01 | DOC EFP | COMMENTS--COMMENTS ON MINOR ALTERATION |
| 02/09/12 | 20122-71389-01 | PUC | BRIEFING PAPERS--FEBRUARY 16, 2012 AGENDA MEETING |
| 02/07/12 | 20122-71325-13 | PUC | NOTICE OF COMMISSION MEETING--REVISED - 2-16-2012 |
| 02/03/12 | 20122-70994-02 | PUC | NOTICE OF COMMISSION MEETING--FEBRUARY 16, 2012 |
| 01/20/12 | 20121-70514-01 | DOC EFP | COMPLIANCE CLOSURE--ACKNOWLEDGEMENT OF RECEIPT |
| 01/19/12 | 20121-70444-01 | PUC | MINUTES--NOVEMBER 29, 2011 AGENDA MEETING |
| 01/18/12 | 20121-70415-01 | DOC EFP | NOTICE--OF MINOR ALTERATION APPLICATION AND COMMENT PERIOD |
| 01/17/12 | 20121-70306-01 | XCEL ENERGY | COMPLIANCE FILING--MONTHLY COMPLAINT SUMMARY |
| 01/10/12 | 20121-70140-05 | NSP & GRE | COMPLIANCE FILING--CECP UPDATE ATTACHMENT 2 PART 3 OF 4 |
| 01/10/12 | 20121-70140-04 | NSP & GRE | COMPLIANCE FILING--CECP UPDATE ATTACHMENT 2 PART 2 OF 4 |
| 01/10/12 | 20121-70140-09 | NSP & GRE | COMPLIANCE FILING--CECP UPDATE ATTACHMENT 3 PART 3 OF 4 |
| 01/10/12 | 20121-70140-03 | NSP & GRE | COMPLIANCE FILING--CECP UPDATE ATTACHMENT 2 PART 1 OF 4 |
| 01/10/12 | 20121-70140-07 | NSP & GRE | COMPLIANCE FILING--CECP UPDATE ATTACHMENT 3 PART 1 OF 4 |
| 01/10/12 | 20121-70140-01 | NSP & GRE | COMPLIANCE FILING--CAPX2020 FILING LETTER FOR CECP UPDATE |
| 01/10/12 | 20121-70140-10 | NSP & GRE | COMPLIANCE FILING--CECP UPDATE ATTACHMENT 3 PART 4 OF 4 |
| 01/10/12 | 20121-70140-08 | NSP & GRE | COMPLIANCE FILING--CECP UPDATE ATTACHMENT 3 PART 2 OF 4 |
| 01/10/12 | 20121-70140-06 | NSP & GRE | COMPLIANCE FILING--CECP UPDATE ATTACHMENT 2 PART 4 OF 4 |
| 01/10/12 | 20121-70140-02 | NSP & GRE | COMPLIANCE FILING--ATTACHMENT 1 TO CECP UPDATE |
| 01/09/12 | 20121-70082-02 | PUC | ORDER--ROUTE PERMIT AMENDMENT E-09-1056 PART 2 OF 3 |
| 01/09/12 | 20121-70099-01 | PUC | LETTER--DNR COMMENT LETTERS |
| 01/09/12 | 20121-70049-01 | ROBERT AND PAULINE UNDERSANDER | RECONSIDERATION--REQUEST FOR RECONSIDERATION |
| 01/09/12 | 20121-70082-01 | PUC | ORDER--ORDER APPROVING MINOR ALTERATIONS AND ISSUING A ROUTE PERMIT AMENDMENT PART 1 OF 3 |
| 01/09/12 | 20121-70082-03 | PUC | ORDER--CERTIFICATE OF SERVICE AND SERVICE LIST E-09-1056 PART 3 OF 3 |
| 01/06/12 | 20121-70033-03 | NORTHERN STATES POWER CO AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 3 OF 8 |
| 01/06/12 | 20121-70033-08 | NORTHERN STATES POWER CO AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 8 OF 8 |
| 01/06/12 | 20121-70033-06 | NORTHERN STATES POWER CO AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 6 OF 8 |
| 01/06/12 | 20121-70033-05 | NORTHERN STATES POWER CO AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 5 OF 8 |
| 01/06/12 | 20121-70033-04 | NORTHERN STATES POWER CO AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 4 OF 8 |
| 01/06/12 | 20121-70033-07 | NORTHERN STATES POWER CO AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 7 OF 8 |
| 01/06/12 | 20121-70033-01 | NORTHERN STATES POWER CO AND GREAT RIVER ENERGY | COMPLIANCE FILING--PLAN AND PROFILE FILING LETTER AND ATTACHMENT 1 PART 1 OF 8 |
| 01/06/12 | 20121-70033-09 | NORTHERN STATES POWER CO AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 2 FINAL PERMITTED ALIGNMENT COMPARISON |
| 01/06/12 | 20121-70033-02 | NORTHERN STATES POWER CO AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 PART 2 OF 8 |
| 12/28/11 | 201112-69670-01 | SCOTT AND BELINDA WALSH | PUBLIC COMMENT |
| 12/28/11 | 201112-69689-01 | PUC | PUBLIC COMMENT |
| 12/27/11 | 201112-69699-01 | PUC | PUBLIC COMMENT |
| 12/21/11 | 201112-69490-01 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | OTHER--APPLICATION FOR A MINOR ALTERATION IN OAK TOWNSHIP |
| 12/19/11 | 201112-69409-01 | PUC | ORDER--ORDER DENYING PETITIONS |
| 12/19/11 | 201112-69409-02 | PUC | ORDER--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 12/19/11 | 201112-69410-01 | DOC EFP | COMPLIANCE CLOSURE--ACKNOWLEDGEMENT OF RECEIPT |
| 12/15/11 | 201112-69289-01 | XCEL ENERGY | COMPLIANCE FILING--MONTHLY COMPLAINT SUMMARY |
| 12/12/11 | 201112-69147-01 | PUC | LETTER--TO DARRIN LAHR AND TIMOTHY LISSON - REVIEW OF COMPLIANCE FILING |
| 12/09/11 | 201112-69120-01 | DOC EFP | COMPLIANCE FILING--RESPONSE TO PLAN AND PROFILE FILING |
| 11/22/11 | 201111-68549-01 | PUC | NOTICE OF COMMISSION MEETING--SERVED TO ADDITIONAL SERVICE LIST |
| 11/22/11 | 201111-68553-01 | PUC | BRIEFING PAPERS--NOVEMBER 29, 2011 AGENDA |
| 11/21/11 | 201111-68476-01 | DOC EFP | BRIEFING PAPERS--COMMENTS AND RECOMMENDATIONS ON PERMIT AMENDMENT |
| 11/17/11 | 201111-68414-03 | PUC | NOTICE OF COMMISSION MEETING--NOVEMBER 29, 2011 |
| 11/15/11 | 201111-68361-01 | XCEL ENERGY | COMPLIANCE FILING--COMPLAINT REPORT SUMMARY |
| 11/14/11 | 201111-68317-01 | PUC | PUBLIC COMMENT |
| 11/14/11 | 201111-68326-01 | DOC EFP | COMPLIANCE FILING--ACKNOWLEDGEMENT OF ECP RECEIPT |
| 11/07/11 | 201111-68186-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 2 MAPBOOK 1 TO 21 |
| 11/07/11 | 201111-68186-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 P AND P PART 9 OF 9 |
| 11/07/11 | 201111-68184-08 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 P AND P PART 1 OF 9 |
| 11/07/11 | 201111-68184-05 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 P AND P PART 5 OF 9 |
| 11/07/11 | 201111-68160-01 | PUC | PUBLIC COMMENT |
| 11/07/11 | 201111-68184-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 P AND P PART 4 OF 9 |
| 11/07/11 | 201111-68184-06 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 P AND P PART 7 OF 9 |
| 11/07/11 | 201111-68186-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 P AND P PART 8 OF 9 |
| 11/07/11 | 201111-68186-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 3 FINAL MOD COMPARISON |
| 11/07/11 | 201111-68184-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 P AND P PART 3 OF 9 |
| 11/07/11 | 201111-68184-07 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 P AND P PART 6 OF 9 |
| 11/07/11 | 201111-68184-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--CAPX FILING LETTER FOR COMPLIANCE FILING INCLUDING PLAN AND PROFILE |
| 11/07/11 | 201111-68184-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMPLIANCE FILING--ATTACHMENT 1 P AND P PART 2 OF 9 |
| 11/04/11 | 201111-68136-01 | MINNESOTA DEPARTMENT OF NATURAL RESOURCES | COMMENTS |
| 11/04/11 | 201111-68137-01 | ROB UNDERSANDER | COMMENTS--RESPONSE TO XCEL COMMENTS |
| 11/04/11 | 201111-68112-01 | CAPX2020 | COMMENTS--CAPX2020 COMMENTS RE E5 LANDOWNERS ROUTE PERMIT AMENDMENT REQUEST |
| 11/03/11 | 201111-68069-04 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 4 PART 2 OF 9 |
| 11/03/11 | 201111-68069-05 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 4 PART 3 OF 9 |
| 11/03/11 | 201111-68069-10 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 4 PART 8 OF 9 |
| 11/03/11 | 201111-68069-07 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 4 PART 5 OF 9 |
| 11/03/11 | 201111-68071-06 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 5 PART 5 OF 7 |
| 11/03/11 | 201111-68071-05 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 5 PART 4 OF 7 |
| 11/03/11 | 201111-68069-01 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP FILING LETTER |
| 11/03/11 | 201111-68069-06 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 4 PART 4 OF 9 |
| 11/03/11 | 201111-68069-09 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 4 PART 7 OF 9 |
| 11/03/11 | 201111-68069-08 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 4 PART 6 OF 9 |
| 11/03/11 | 201111-68069-03 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 4 PART 1 OF 9 |
| 11/03/11 | 201111-68071-01 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 4 PART 9 OF 9 |
| 11/03/11 | 201111-68069-02 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP AND TABS 1 TO 3 OF 5 |
| 11/03/11 | 201111-68071-07 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 5 PART 6 OF 7 |
| 11/03/11 | 201111-68071-02 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 5 PART 1 OF 7 |
| 11/03/11 | 201111-68071-08 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 5 PART 7 OF 7 |
| 11/03/11 | 201111-68071-03 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 5 PART 2 OF 7 |
| 11/03/11 | 201111-68071-04 | NORTHERN STATES POWER COMPANY | COMPLIANCE FILING--XCEL CAPX CECP TAB 5 PART 3 OF 7 |
| 11/02/11 | 201111-68016-01 | RICH AND KAREN HELD | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68013-01 | CHRISTINE FREIDERICHS | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68015-01 | BRUCE AND VICKY HAGBERG | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68027-01 | PETE STEICHEN | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-67998-01 | BILL AND ANN DALTON | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68032-01 | JOHN UNDERSANDER | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68025-01 | GARY SCHNEIDER | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68018-01 | ROD AND KARRIE LANGE | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68037-01 | TIM AND BRENDA WEISBRICH | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68031-01 | HAL AND PAT UNDERSANDER | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68020-01 | BROOKS AND COLLEEN MARQUARDT | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-67989-02 | PATRICK AND PERNINA BURKE | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68034-01 | MR. AND NICOLE VALLEY | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68039-01 | JAMES WILLARD | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68024-01 | ARLAN AND VIOLA SCHLAGEL | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68026-01 | DEBRA AND JAMIE SCHRAMEL | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-67989-01 | PATRICK AND PERNINA BURKE | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68042-01 | BARRY AND WANDA ZENNER | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68001-01 | RONALD AND MARY EIKMEIRER | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68041-01 | JUDY ZABINSKI | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68035-01 | TOM AND PATTY WALETZKO | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68033-01 | ROB AND PAULINE UNDERSANDER | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68005-01 | RONALD AND MARY EIKMEIRER | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68019-01 | DONNA AND DARREL LONG | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68036-01 | LEE WEISBRICH | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68022-01 | TREVOR AND HEIDI MARQUARDT | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-67988-01 | JAMES AND DELPHINE BROWN | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68038-01 | DELROSE WILLARD | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68023-01 | TERRA O'NEIL AND LYNN RICHERT | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68017-01 | TODD AND MARY HELD | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68000-01 | KEN AND LINDA EIKMEIRER | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68010-01 | DAN FINKEN | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68028-01 | SCOTT AND MARYBETH THEISEN | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68030-01 | SUSAN AND MARK THEISEN | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-67999-01 | MATT AND CINDI DORWEILER | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/02/11 | 201111-68040-01 | ROBERT J WILLARD | COMMENTS--IN SUPPORT OF UNDERSANDER ROUTE AMENDMENT |
| 11/01/11 | 201111-67937-01 | VIRGINIA SCHREIFELS | COMMENTS |
| 11/01/11 | 201111-67952-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMMENTS--PERMITTEES CLARIFYING COMMENTS ON ROUTE PERMIT AMENDMENT REQUEST |
| 10/25/11 | 201110-67676-01 | DOC EFP | COMPLIANCE CLOSURE--ACKNOWLEDGEMENT OF RECEIPT |
| 10/21/11 | 201110-67592-01 | CAPX2020 | LETTER--CAPX2020 AFFIDAVIT OF MAILING NOTICE TO LANDOWNERS RE UNDERSANDER ALIGNMENT REQUEST |
| 10/20/11 | 201110-67553-01 | PUC | NOTICE OF COMMENT PERIOD |
| 10/18/11 | 201110-67491-01 | DOC EFP | PUBLIC COMMENT--PA - DNR |
| 10/18/11 | 201110-67491-04 | DOC EFP | PUBLIC COMMENT--PA - ADJ 9C |
| 10/18/11 | 201110-67491-06 | DOC EFP | PUBLIC COMMENT--PA - ADJ 13 |
| 10/18/11 | 201110-67455-01 | XCEL ENERGY | COMPLIANCE FILING--FARGO TO ST. CLOUD COMPLAINT REPORT SUMMARY OCTOBER 2011 |
| 10/18/11 | 201110-67491-03 | DOC EFP | PUBLIC COMMENT--PA - ADJ 4.1 |
| 10/18/11 | 201110-67491-07 | DOC EFP | PUBLIC COMMENT--PA - NON-SPECIFIC |
| 10/18/11 | 201110-67491-05 | DOC EFP | PUBLIC COMMENT--PA - ADJ 11 |
| 10/18/11 | 201110-67491-02 | DOC EFP | PUBLIC COMMENT--PA - ADJ 2 |
| 10/17/11 | 201110-67452-01 | NOCAPX AND UNITED CITIZENS ACTION NETWORK | COMMENTS---RE VIRGIL FUCHS - DENY ADJUSTMENT 13 |
| 10/17/11 | 201110-67402-01 | PUC | PUBLIC COMMENT |
| 10/14/11 | 201110-67378-01 | VIRGIL FUCHS | LETTER--- OPPOSING PERMIT AMENDMENT REQUEST |
| 10/13/11 | 201110-67275-01 | ROB AND PAULINE UNDERSANDER | LETTER--LETTER REQUESTING FULL COMMISSIONERS REVIEW |
| 10/10/11 | 201110-67175-01 | PUC | PUBLIC COMMENT |
| 10/07/11 | 201110-67145-01 | XCEL ENERGY | OTHER--ROUTE ADJUSTMENT 4.1 AND 4 COMPARISON SUMMARY FOR EDOC 20119-66518-03 |
| 10/04/11 | 201110-66945-01 | PUC | PUBLIC COMMENT |
| 09/29/11 | 20119-66736-01 | DOC | NOTICE--OF PERMIT AMENDMENT REQUEST |
| 09/26/11 | 20119-66620-01 | ROB AND PAULINE UNDERSANDER | LETTER--LETTER REQUESTING ROUTE AMENDMENT 15 DELAY PENDING ATTORNEY GENERAL INVESTIGATION |
| 09/22/11 | 20119-66560-01 | PUC | LETTER--TO ROBERT AND PAULINE UNDERSANDER, ET AL. |
| 09/21/11 | 20119-66518-02 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | OTHER--CAPX2020 OVERVIEW MAP AND ADJUSTMENTS 2 AND 3 TO APP FOR APPROVAL OF ROUTE PERMIT AMENDMENT |
| 09/21/11 | 20119-66518-06 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | OTHER--CAPX2020 ADJUSTMENTS 11 13 TO APP FOR APPROVAL OF ROUTE PERMIT AMENDMENT |
| 09/21/11 | 20119-66518-07 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | OTHER--CAPX2020 ADJUSTMENT 15 TO APP FOR APPROVAL OF ROUTE PERMIT AMENDMENT |
| 09/21/11 | 20119-66518-01 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | OTHER--CAPX2020 FILING LETTER FOR APPLICATION FOR APPROVAL OF ROUTE PERMIT AMENDMENT |
| 09/21/11 | 20119-66518-03 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | OTHER--CAPX2020 ADJUSTMENTS 4 4.1 AND 5 TO APP FOR APPROVAL OF ROUTE PERMIT AMENDMENT |
| 09/21/11 | 20119-66518-05 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | OTHER--CAPX2020 ADJUSTMENT 9C TO APP FOR APPROVAL OF ROUTE PERMIT AMENDMENT |
| 09/21/11 | 20119-66518-04 | NORTHERN STATES POWER COMPANY, GREAT RIVER ENERGY | OTHER--CAPX2020 ADJUSTMENTS 6 8 9W TO APP FOR APPROVAL OF ROUTE PERMIT AMENDMENT |
| 09/15/11 | 20119-66401-01 | XCEL ENERGY | COMPLIANCE FILING |
| 09/14/11 | 20119-66344-05 | ROB AND PAULINE UNDERSANDER | OTHER--ROUTE AMENDMENT REQUEST - TO |
| 09/14/11 | 20119-66344-04 | ROB AND PAULINE UNDERSANDER | OTHER--ROUTE AMENDMENT REQUEST - TW |
| 09/14/11 | 20119-66344-01 | ROB AND PAULINE UNDERSANDER | OTHER--ROUTE AMENDMENT REQUEST - RLU. |
| 09/14/11 | 20119-66344-02 | ROB AND PAULINE UNDERSANDER | OTHER--ROUTE AMENDMENT REQUEST - KE |
| 09/14/11 | 20119-66344-03 | ROB AND PAULINE UNDERSANDER | OTHER--ROUTE AMENDMENT REQUEST - HU |
| 06/30/11 | 20116-64346-01 | PUC | MINUTES--JUNE 10, 2011 AGENDA MEETING |
| 06/28/11 | 20116-64164-01 | PUC | NOTICE--NOTICE OF AVAILABILITY OF FINAL ORDER |
| 06/27/11 | 20116-64131-01 | PUC | PUBLIC COMMENT |
| 06/24/11 | 20116-64023-02 | PUC | ORDER--CERTIFICATE OF SERVICE AND SERVICE LIST |
| 06/24/11 | 20116-64023-01 | PUC | ORDER--FINDINGS OF FACT, CONCLUSIONS OF LAW, AND ORDER ISSUING AN HVTL ROUTE PERMIT TO XCEL ENERGY AND GREAT RIVER ENERGY |
| 06/20/11 | 20116-63799-01 | PUC | PUBLIC COMMENT |
| 06/13/11 | 20116-63516-01 | PUC | PUBLIC COMMENT |
| 06/06/11 | 20116-63291-01 | PUC | PUBLIC COMMENT |
| 06/06/11 | 20116-63295-01 | PUC | PUBLIC COMMENT |
| 06/06/11 | 20116-63280-01 | DOC EFP | BRIEFING PAPERS--SUPPLEMENTAL COMMENTS AND RECOMMENDATIONS |
| 06/02/11 | 20116-63224-01 | MN/DOT | LETTER |
| 05/27/11 | 20115-63028-06 | DOC EFP | BRIEFING PAPERS--MAPS-SAUK CENTRE TO STC-PT1 |
| 05/27/11 | 20115-63028-07 | DOC EFP | BRIEFING PAPERS--MAPS-SAUK CENTRE TO STC-PT2 |
| 05/27/11 | 20115-63028-05 | DOC EFP | BRIEFING PAPERS--MAPS-ALEX TO SAUK CENTRE |
| 05/27/11 | 20115-63028-01 | DOC EFP | BRIEFING PAPERS--COMMENTS AND PROPOSED FINDINGS AND PERMIT |
| 05/27/11 | 20115-62994-03 | PUC | NOTICE OF COMMISSION MEETING--JUNE 10, 2011 |
| 05/27/11 | 20115-63028-03 | DOC EFP | BRIEFING PAPERS--MAPS-ND TO ALEX-PT 2 |
| 05/27/11 | 20115-63028-02 | DOC EFP | BRIEFING PAPERS--MAPS-ND TO ALEX-PT 1 |
| 05/27/11 | 20115-63015-01 | PUC | NOTICE--COMMISSION MEETING |
| 05/27/11 | 20115-63028-04 | DOC EFP | BRIEFING PAPERS--MAPS-ND TO ALEX-PT3 |
| 05/24/11 | 20115-62851-01 | PUC | PUBLIC COMMENT |
| 05/17/11 | 20115-62634-01 | PUC | PUBLIC COMMENT |
| 05/16/11 | 20115-62621-01 | OAH | LETTER |
| 05/12/11 | 20115-62479-01 | PUC | PUBLIC COMMENT |
| 05/10/11 | 20115-62391-01 | PUC | PUBLIC COMMENT |
| 05/10/11 | 20115-62386-01 | MICHAEL ZIMMER | OTHER--LETTER |
| 05/10/11 | 20115-62415-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | OTHER--APPLICANTS EXCEPTIONS TO ALJ REPORT |
| 05/10/11 | 20115-62430-01 | NOCAPX 2020 UNITED CITIZEN ACTION NETWORK AND NORTH ROUTE CITIZENS ALLIANCE | OTHER--EXCEPTIONS TO ALJ RECOMMENDATION |
| 05/10/11 | 20115-62417-01 | MINNESOTA DEPARTMENT OF NATURAL RESOURCES | COMMENTS |
| 05/10/11 | 20115-62409-01 | AVON TOWNSHIP | OTHER--LETTER TO BURL HAAR FILING SUPPORT TO ROUTE AND EXCEPTIONS |
| 05/10/11 | 20115-62409-02 | AVON TOWNSHIP | OTHER--AVON TOWNSHIP SUPPORT FOR ROUTE SELECTION AND EXCEPTIONS |
| 05/10/11 | 20115-62433-01 | OAH | LETTER--LETTERS FILED WITH OAH |
| 05/10/11 | 20115-62386-02 | MICHAEL ZIMMER | OTHER--ORIGINAL LAND PURCHASE AGREEMENT |
| 05/10/11 | 20115-62409-03 | AVON TOWNSHIP | OTHER--CERTIFICATE OF SERVICE |
| 05/02/11 | 20115-62154-01 | PUC | NOTICE--NEXT STEPS IN COMMISSION PROCESS |
| 04/28/11 | 20114-61861-03 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 2 TO MNDOT EXCEPTION APPLICATION PAGE 1 OF 4 |
| 04/28/11 | 20114-61861-07 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 3 TO MNDOT EXCEPTION APPLICATION PAGE 1 OF 4 |
| 04/28/11 | 20114-61861-08 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 3 TO MNDOT EXCEPTION APPLICATION PAGE 2 OF 4 |
| 04/28/11 | 20114-61861-05 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 2 TO MNDOT EXCEPTION APPLICATION PAGE 3 OF 4. |
| 04/28/11 | 20114-61861-06 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 2 TO MNDOT EXCEPTION APPLICATION PAGE 4 OF 4. |
| 04/28/11 | 20114-61862-01 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 4 TO MNDOT EXCEPTION APPLICATION |
| 04/28/11 | 20114-61861-09 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 3 TO MNDOT EXCEPTION APPLICATION PAGE 3 OF 4 |
| 04/28/11 | 20114-61861-02 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 1 TO MNDOT EXCEPTION APPLICATION |
| 04/28/11 | 20114-61862-02 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 5 TO MNDOT EXCEPTION APPLICATION PAGE 1 OF 9. |
| 04/28/11 | 20114-61861-04 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 2 TO MNDOT EXCEPTION APPLICATION PAGE 2 OF 4 |
| 04/28/11 | 20114-61862-05 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 5 TO MNDOT EXCEPTION APPLICATION PAGE 4 OF 9 |
| 04/28/11 | 20114-61862-10 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 5 TO MNDOT EXCEPTION APPLICATION PAGE 9 OF 9. |
| 04/28/11 | 20114-61861-10 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 3 TO MNDOT EXCEPTION APPLICATION PAGE 4 OF 4 |
| 04/28/11 | 20114-61862-04 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 5 TO MNDOT EXCEPTION APPLICATION PAGE 3 OF 9. |
| 04/28/11 | 20114-61862-06 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 5 TO MNDOT EXCEPTION APPLICATION PAGE 5 OF 9. |
| 04/28/11 | 20114-61862-08 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 5 TO MNDOT EXCEPTION APPLICATION PAGE 7 OF 9 |
| 04/28/11 | 20114-61861-01 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO-STC_EXCEPTION_REQUEST_FOR |
| 04/28/11 | 20114-61862-03 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 5 TO MNDOT EXCEPTION APPLICATION PAGE 2 OF 9 |
| 04/28/11 | 20114-61862-09 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 5 TO MNDOT EXCEPTION APPLICATION PAGE 8 OF 9 |
| 04/28/11 | 20114-61862-07 | NORTHERN STATES POWER COMPANY | LETTER--XCEL_FARGO_ATTACHMENT 5 TO MNDOT EXCEPTION APPLICATION PAGE 6 OF 9 |
| 04/25/11 | 20114-61700-01 | OAH | REPORT--FINDINGS OF FACT, CONCLUSIONS AND RECOMMENDATION |
| 04/04/11 | 20114-60984-01 | DOC OES EFP | LETTER--LETTER TO ALJ HEYDINGER |
| 03/31/11 | 20113-60808-01 | OAH | LETTER--LETTER SUBMITTING AMENDED EXHIBIT LIST |
| 03/23/11 | 20113-60562-01 | OAH | LETTER--LETTER FROM ALJ HEYDINGER TO L. AGRIMONTI AND K. F. HAMMEL |
| 03/04/11 | 20113-60116-01 | DOC OES EFP | COMMENTS--OES EFP COMMENTS |
| 03/04/11 | 20113-60098-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | REPLY BRIEF |
| 02/18/11 | 20112-59704-01 | AVON TOWNSHIP | BRIEF--FILING LETTER AND CERTIFICATE OF SERVICE |
| 02/18/11 | 20112-59680-01 | INTERVENOR SAINT JOHN'S ABBEY/UNIVERSITY | BRIEF |
| 02/18/11 | 20112-59681-01 | SAINT JOHN'S ABBEY/UNIVERSITY | BRIEF--AMENDED COVER LETTER W/ SERVICE LIST |
| 02/18/11 | 20112-59679-01 | INTERVENOR SAINT JOHN'S ABBEY/UNIVERSITY | BRIEF--COVER |
| 02/18/11 | 20112-59711-01 | NOCAPX U-CAN AND NORCA | BRIEF--- ATTACHMENT A |
| 02/18/11 | 20112-59704-03 | AVON TOWNSHIP | BRIEF--PROP. FINDINGS OF FACT, CONCLUSIONS OF LAW AND RECOMMENDATION |
| 02/18/11 | 20112-59704-02 | AVON TOWNSHIP | BRIEF--POST HEARING BRIEF |
| 02/18/11 | 20112-59709-01 | NOCAPX U-CAN AND NORCA | BRIEF--POST HEARING BRIEF |
| 02/10/11 | 20112-59408-01 | OAH | LETTER--LETTER FROM ALJ HEYDINGER |
| 02/10/11 | 20112-59408-02 | OAH | LETTER--AMENDED EXHIBIT LIST |
| 02/10/11 | 20112-59437-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | LETTER |
| 02/07/11 | 20112-59280-01 | DOC OES | LETTER--- TO BEVERLY JONES HEYDINGER |
| 01/31/11 | 20111-59084-01 | DOC OES | EXHIBITS - HEARING--UPDATED OES EXHIBIT LIST |
| 01/28/11 | 20111-58987-02 | APPLICANTS NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | BRIEF--APPLICANTS POST HEARING BRIEF |
| 01/28/11 | 20111-58987-01 | APPLICANTS NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | BRIEF--FILING LETTER AND CERTIFICATE OF SERVICE |
| 01/28/11 | 20111-58987-03 | APPLICANTS NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | BRIEF--FINDINGS OF FACT, CONCLUSIONS OF LAW AND RECOMMENDATION |
| 01/27/11 | 20111-58943-01 | OAH | PUBLIC COMMENT--TWO PUBLIC COMMENTS FILED LATE |
| 01/27/11 | 20111-58942-01 | APPLICANTS NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | LETTER--LETTER TO ALJ HEYDINGER REGARDING LATE FILED EXHIBITS |
| 01/20/11 | 20111-58708-01 | OAH | OTHER--FARGO EXHIBIT LIST |
| 01/19/11 | 20111-58663-02 | OAH | PUBLIC COMMENT--NO. 2 |
| 01/19/11 | 20111-58663-03 | OAH | PUBLIC COMMENT--NO. 3 |
| 01/19/11 | 20111-58663-05 | OAH | PUBLIC COMMENT--NO. 4 |
| 01/19/11 | 20111-58663-09 | OAH | PUBLIC COMMENT--FILED LATE |
| 01/19/11 | 20111-58663-01 | OAH | PUBLIC COMMENT--NO. 1 |
| 01/19/11 | 20111-58663-04 | OAH | PUBLIC COMMENT--NO. 3A |
| 01/19/11 | 20111-58663-06 | OAH | PUBLIC COMMENT--NO. 5 |
| 01/19/11 | 20111-58663-07 | OAH | PUBLIC COMMENT--NO. 6 |
| 01/19/11 | 20111-58663-08 | OAH | PUBLIC COMMENT--NO. 6A |
| 01/19/11 | 20111-58694-01 | DOC OES | EXHIBITS - HEARING---- EX 27 |
| 01/11/11 | 20111-58417-06 | OAH | PUBLIC COMMENT |
| 01/11/11 | 20111-58417-01 | OAH | PUBLIC COMMENT |
| 01/11/11 | 20111-58379-01 | DOC OES | NOTICE--OF AVAILABILITY OF FINAL EIS |
| 01/11/11 | 20111-58417-05 | OAH | PUBLIC COMMENT |
| 01/11/11 | 20111-58417-07 | OAH | PUBLIC COMMENT |
| 01/11/11 | 20111-58417-04 | OAH | PUBLIC COMMENT |
| 01/11/11 | 20111-58417-03 | OAH | PUBLIC COMMENT |
| 01/11/11 | 20111-58417-02 | OAH | PUBLIC COMMENT |
| 01/10/11 | 20111-58323-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | OTHER--AFFIDAVT ATTESTING PUBLIC AND EVIDENTIARY HEARING TRANSCRIPTS MAILED TO AREA LIBRARIES. |
| 01/07/11 | 20111-58289-01 | DOC OES | OTHER--FEIS - TEXT |
| 01/07/11 | 20111-58289-05 | DOC OES | OTHER--FEIS - APPENDIX A - COMMENTS4 |
| 01/07/11 | 20111-58289-06 | DOC OES | OTHER--FEIS - APPENDIX B - AGENCY COMMENTS |
| 01/07/11 | 20111-58289-07 | DOC OES | OTHER--FEIS - APPENDIX D - BLANDINGS TURTLE |
| 01/07/11 | 20111-58289-02 | DOC OES | OTHER--FEIS - APPENDIX A - COMMENTS1 |
| 01/07/11 | 20111-58294-08 | DOC OES | OTHER--FEIS - APPENDIX C - MAPS 99-102 |
| 01/07/11 | 20111-58294-07 | DOC OES | OTHER--FEIS - APPENDIX C - MAPS 85-98 |
| 01/07/11 | 20111-58289-03 | DOC OES | OTHER--FEIS - APPENDIX A - COMMENTS2 |
| 01/07/11 | 20111-58294-06 | DOC OES | OTHER--FEIS - APPENDIX C - MAPS 74-84 |
| 01/07/11 | 20111-58289-04 | DOC OES | OTHER--FEIS - APPENDIX A - COMMENTS3 |
| 01/07/11 | 20111-58294-02 | DOC OES | OTHER--FEIS - APPENDIX C - MAPS 12-24 |
| 01/07/11 | 20111-58294-01 | DOC OES | OTHER--FEIS - APPENDIX C - MAPS 1-11 |
| 01/07/11 | 20111-58294-03 | DOC OES | OTHER--FEIS - APPENDIX C - MAPS 25-43 |
| 01/07/11 | 20111-58294-04 | DOC OES | OTHER--FEIS - APPENDIX C - MAPS 44-58 |
| 01/07/11 | 20111-58294-05 | DOC OES | OTHER--FEIS - APPENDIX C - MAPS 59-73 |
| 01/06/11 | 20111-58189-03 | COURT REPORTER | EXHIBITS - HEARING--EX 32 |
| 01/06/11 | 20111-58189-10 | COURT REPORTER | EXHIBITS - HEARING--EX 48 |
| 01/06/11 | 20111-58189-01 | COURT REPORTER | EXHIBITS - HEARING--EX 2 ERRATA |
| 01/06/11 | 20111-58189-08 | COURT REPORTER | EXHIBITS - HEARING--EX 46 |
| 01/06/11 | 20111-58189-02 | COURT REPORTER | EXHIBITS - HEARING--EX 28 |
| 01/06/11 | 20111-58189-04 | COURT REPORTER | EXHIBITS - HEARING--EX 33 |
| 01/06/11 | 20111-58191-03 | COURT REPORTER | EXHIBITS - HEARING--EX 51 |
| 01/06/11 | 20111-58189-07 | COURT REPORTER | EXHIBITS - HEARING--EX 43 |
| 01/06/11 | 20111-58189-09 | COURT REPORTER | EXHIBITS - HEARING--EX 47 |
| 01/06/11 | 20111-58189-06 | COURT REPORTER | EXHIBITS - HEARING--EX 42 |
| 01/06/11 | 20111-58189-05 | COURT REPORTER | EXHIBITS - HEARING--EX 34 |
| 01/06/11 | 20111-58191-01 | COURT REPORTER | EXHIBITS - HEARING--EX 50 |
| 01/06/11 | 20111-58191-04 | COURT REPORTER | EXHIBITS - HEARING--EX 52 |
| 01/06/11 | 20111-58191-02 | COURT REPORTER | EXHIBITS - HEARING--EX 50A |
| 01/05/11 | 20111-58170-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMMENTS |
| 01/05/11 | 20111-58173-01 | MN/DOT | LETTER |
| 01/04/11 | 20111-58107-02 | OAH | PUBLIC COMMENT--PUBLIC COMMENTS - PART 4 |
| 01/04/11 | 20111-58138-01 | DAVID CAMPAGNA & ANN MARIE STOCK | LETTER |
| 01/04/11 | 20111-58104-01 | OAH | PUBLIC COMMENT--PUBLIC COMMENTS, PART 1 |
| 01/04/11 | 20111-58107-01 | OAH | PUBLIC COMMENT--PUBLIC COMMENTS - PART 3 |
| 01/04/11 | 20111-58106-01 | OAH | PUBLIC COMMENT--PUBLIC COMMENTS - PART 2 |
| 12/22/10 | 201012-57785-02 | OAH | PUBLIC COMMENT--MCCOY PROPERTY COMMENT PART 1 OF 2 |
| 12/22/10 | 201012-57785-03 | OAH | PUBLIC COMMENT--MCCOY PROPERTY COMMENT PART 2 OF 2 |
| 12/22/10 | 201012-57785-04 | OAH | PUBLIC COMMENT--VARIOUS COMMENTS THROUGH DECEMBER 22 |
| 12/22/10 | 201012-57785-01 | OAH | PUBLIC COMMENT--VAROUS COMMENTS FROM NOVEMBER 17 THROUGH DECEMBER 8 |
| 12/20/10 | 201012-57707-01 | PUC | PUBLIC COMMENT |
| 12/15/10 | 201012-57506-01 | OAH | PUBLIC COMMENT--LIGHTER COPY OF DONABAUER PROPERTY LOCATION |
| 12/15/10 | 201012-57503-01 | OAH | PUBLIC COMMENT--PUBLIC COMMENTS |
| 12/14/10 | 201012-57444-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | LETTER |
| 12/13/10 | 201012-57410-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | LETTER--SUPPLEMENTAL PROJECT INFORMATION |
| 12/09/10 | 201012-57310-02 | OAH | PUBLIC COMMENT--2 OF 2 |
| 12/09/10 | 201012-57310-01 | OAH | PUBLIC COMMENT--1 OF 2 |
| 12/07/10 | 201012-57217-01 | MN/DOT | LETTER |
| 12/06/10 | 201012-57170-05 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 22 |
| 12/06/10 | 201012-57168-08 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 8 |
| 12/06/10 | 201012-57170-01 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 18 |
| 12/06/10 | 201012-57169-08 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 15 |
| 12/06/10 | 201012-57168-09 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 9 |
| 12/06/10 | 201012-57169-02 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 11B |
| 12/06/10 | 201012-57169-05 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 12 |
| 12/06/10 | 201012-57168-07 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 7 |
| 12/06/10 | 201012-57169-01 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 11A |
| 12/06/10 | 201012-57171-01 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 28 |
| 12/06/10 | 201012-57171-09 | COURT REPORTER | EXHIBITS - HEARING--SIGNIN SHEETS FOR PUBLIC HEARINGS 11-16 THRU 11-18-2010 |
| 12/06/10 | 201012-57168-10 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 10 |
| 12/06/10 | 201012-57169-10 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 17 |
| 12/06/10 | 201012-57174-01 | AVON TOWNSHIP | OTHER--RESPONSE OF AVON TOWNSHIP TO MOTION TO STRIKE BY NOCAPX2020 |
| 12/06/10 | 201012-57178-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | MOTION--APPLICANTS OPPOSITION TO NOCAPX MOTIONS TO STRIKE AND SUBSTITUTE TESTIMONY |
| 12/06/10 | 201012-57168-03 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 3 |
| 12/06/10 | 201012-57169-07 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 14 |
| 12/06/10 | 201012-57169-03 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 11C |
| 12/06/10 | 201012-57171-06 | COURT REPORTER | EXHIBITS - HEARING--SAUK CENTRE SIGNIN SHEETS |
| 12/06/10 | 201012-57171-05 | COURT REPORTER | EXHIBITS - HEARING--MELROSE SIGNIN SHEETS |
| 12/06/10 | 201012-57170-07 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 24 |
| 12/06/10 | 201012-57171-04 | COURT REPORTER | EXHIBITS - HEARING--COLD SPRING SIGNIN SHEETS |
| 12/06/10 | 201012-57171-07 | COURT REPORTER | EXHIBITS - HEARING--ST CLOUD SIGNIN SHEETS |
| 12/06/10 | 201012-57169-06 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 13 |
| 12/06/10 | 201012-57170-08 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 25 |
| 12/06/10 | 201012-57174-02 | AVON TOWNSHIP | OTHER--CERTIFICATE OF SERVICE |
| 12/06/10 | 201012-57168-04 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 4 |
| 12/06/10 | 201012-57170-10 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 27 |
| 12/06/10 | 201012-57169-04 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 11D |
| 12/06/10 | 201012-57169-09 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 16 |
| 12/06/10 | 201012-57170-04 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 21 |
| 12/06/10 | 201012-57171-02 | COURT REPORTER | EXHIBITS - HEARING--NOCAPX-UCAN-NORCA EXHIBIT 12 |
| 12/06/10 | 201012-57171-03 | COURT REPORTER | EXHIBITS - HEARING--ALBANY SIGNIN SHEETS |
| 12/06/10 | 201012-57168-02 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 2 |
| 12/06/10 | 201012-57168-06 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 6 |
| 12/06/10 | 201012-57170-06 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 23 |
| 12/06/10 | 201012-57168-05 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 5 |
| 12/06/10 | 201012-57168-01 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 1 |
| 12/06/10 | 201012-57170-02 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 19 |
| 12/06/10 | 201012-57170-09 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 26 |
| 12/06/10 | 201012-57174-03 | AVON TOWNSHIP | OTHER--LETTER TO JUDGE HEYDINGER AVON TWSHP RESPONSE TO MTN TO STRIKE |
| 12/06/10 | 201012-57171-08 | COURT REPORTER | EXHIBITS - HEARING--ST JOSEPH SIGNIN SHEETS |
| 12/06/10 | 201012-57170-03 | COURT REPORTER | EXHIBITS - HEARING--PUBLIC EXHIBIT 20 |
| 12/03/10 | 201012-57160-01 | NOCAPX 2020 U-CAN AND NORCA | MOTION--OBJECTION - MOTION TO STRIKE |
| 12/02/10 | 201012-57112-01 | RENEWABLE ENERGY SYSTEMS AMERICAS INC. | COMMENTS--SUPPORTING CAPX FARGO-ST. CLOUD ROUTE PERMIT |
| 12/01/10 | 201012-57019-01 | NOCAPX2020 U-CAN AND NORCA | EXTENSIONVARIANCE REQUEST--REQUEST FOR LEAVE TO SUBMIT RESPONSIVE SURREBUTTAL |
| 12/01/10 | 201012-57039-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | TESTIMONY--CORRECTED SCHEDULE 6 TO VALBERG SURREBUTTAL |
| 11/30/10 | 201011-56977-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | SURREBUTTAL--DANIEL KLINE AND SCHEDULES 1 - 3 |
| 11/30/10 | 201011-56977-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | SURREBUTTAL--COVER |
| 11/30/10 | 201011-56970-03 | AVON TOWNSHIP | EXHIBITS - HEARING--CERTIFICATE OF SERVICE |
| 11/30/10 | 201011-56970-01 | AVON TOWNSHIP | EXHIBITS - HEARING--LIST OF EXHIBITS BY AVON TOWNSHIP |
| 11/30/10 | 201011-56989-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | LETTER--WITNESS AVAILABILITY |
| 11/30/10 | 201011-56932-01 | NORTHERN STATES POWER COMPANY ANAD GREAT RIVER ENERGY | AFFIDAVIT OF PUBLICATION--- FOR NOTICE OF APPLICATION |
| 11/30/10 | 201011-56986-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | EXHIBITS - HEARING |
| 11/30/10 | 201011-56961-01 | INTERVENER SAINT JOHN'S ABBEY/UNIVERSITY OF ST. JOHN'S | EXHIBITS - HEARING |
| 11/30/10 | 201011-56977-04 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | SURREBUTTAL--DR. PETER A. VALBERG AND SCHEDULES 1 - 6 |
| 11/30/10 | 201011-56977-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | SURREBUTTAL--DARRIN LAHR AND SCHEDULES 15 AND 16 |
| 11/30/10 | 201011-56970-02 | AVON TOWNSHIP | EXHIBITS - HEARING--LIST OF WITNESSES BY AVON TOWNSHIP |
| 11/17/10 | 201011-56631-01 | AVON TOWNSHIP | REBUTTAL---TESTIMONY OF KIM A. CHAPMAN |
| 11/17/10 | 201011-56629-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | REBUTTAL---TESTIMONY AND SCHEDULES 8-14 OF DARRIN LAHR |
| 11/17/10 | 201011-56640-02 | NSP AND GREAT RIVER ENERGY | EXHIBITS - HEARING--EXHIBITS 4A-4W-PART 3 OF 4 |
| 11/17/10 | 201011-56631-02 | AVON TOWNSHIP | REBUTTAL--CERTIFICATE OF SERVICE |
| 11/17/10 | 201011-56640-03 | NSP AND GREAT RIVER ENERGY | EXHIBITS - HEARING--EXHIBITS 4A-4W-PART 1 OF 4 |
| 11/17/10 | 201011-56640-04 | NSP AND GREAT RIVER ENERGY | EXHIBITS - HEARING--EXHIBITS 4A-4W-PART 4 OF 4 |
| 11/17/10 | 201011-56619-01 | SAINT JOHN'S ABBEY/UNIVERSITY | REBUTTAL |
| 11/17/10 | 201011-56640-01 | NSP AND GREAT RIVER ENERGY | EXHIBITS - HEARING--EXHIBITS 4A-4W-PART 2 OF 4 |
| 11/15/10 | 201011-56485-01 | OAH | PUBLIC COMMENT--VARIOUS PUBLIC COMMENTS |
| 11/12/10 | 201011-56443-01 | DOC OES | NOTICE--DRAFT EIS AVAILABILITY AND MEETING NOTICE |
| 11/12/10 | 201011-56442-02 | DOC OES | NOTICE--AFFIDAVIT OF PUBLICATION |
| 11/12/10 | 201011-56442-01 | DOC OES | NOTICE--NEWSPAPER NOTICE OF SCOPING MEETING |
| 11/12/10 | 201011-56457-01 | DOC OES | EXHIBITS - HEARING--OES EXHIBIT LIST WITH LINKS |
| 11/12/10 | 201011-56455-01 | OAH | LETTER--NOVEMBER 12, 2010 LETTER FROM JUDGE HEYDINGER TO CAROL OVERLAND |
| 11/12/10 | 201011-56443-02 | DOC OES | NOTICE--AFFIDAVIT OF PUBLICATION |
| 11/09/10 | 201011-56320-01 | NOCAPX U-CAN AND NORCA | LETTER--LETTER - WITHDRAWAL OF SUBPOENA AND WITNESS PRESENCE AT HEARINGS |
| 11/08/10 | 201011-56294-01 | DOC OES | NOTICE--EQB MONITOR NOTICE OF DEIS AVAILABILITY |
| 11/05/10 | 201011-56263-01 | OAH | LETTER--- FROM ALJ HEYDINGER TO PARTIES |
| 11/04/10 | 201011-56186-01 | AVON TOWNSHIP | LETTER--LETTER TO JUDGE HEYDINGER |
| 11/03/10 | 201011-56173-01 | SAINT JOHN'S ABBEY/UNIVERSITY | LETTER |
| 11/01/10 | 201010-56019-01 | NOCAPX AND U-CAN AND NORCA | OTHER--SUBPOENA REQUESTS - DNR DOT |
| 11/01/10 | 201011-56046-01 | DOC OES | NOTICE--OF PUBLIC HEARING |
| 10/29/10 | 201010-55995-01 | AVON TOWNSHIP | TESTIMONY--DIRECT TESTIMONY OF KIM A. CHAPMAN WITH SCHEDULE 1 |
| 10/29/10 | 201010-55994-03 | AVON TOWNSHIP | TESTIMONY--CERTIFICATE OF SERVICE - BRESNAHAN TESTIMONY |
| 10/29/10 | 201010-56014-04 | INTERVENER SAINT JOHN'S ABBEY/UNIVERSITY | TESTIMONY--CHAPMAN |
| 10/29/10 | 201010-56014-03 | INTERVENER SAINT JOHN'S ABBEY/UNIVERSITY | TESTIMONY--RESTANI |
| 10/29/10 | 201010-56014-08 | INTERVENER SAINT JOHN'S ABBEY/UNIVERSITY | TESTIMONY--KROLL PART 2 OF 3 |
| 10/29/10 | 201010-56015-01 | INTERVENER SAINT JOHN'S ABBEY/UNIVERSITY | TESTIMONY--KROLL PART 1 OF 3 |
| 10/29/10 | 201010-56014-07 | INTERVENER SAINT JOHN'S ABBEY/UNIVERSITY | TESTIMONY--KROLL PART 3 OF 3 |
| 10/29/10 | 201010-56014-06 | INTERVENER SAINT JOHN'S ABBEY/UNIVERSITY | TESTIMONY--ROBBINS 2 OF 2 |
| 10/29/10 | 201010-55995-04 | AVON TOWNSHIP | TESTIMONY--CERTIFICATE OF SERVICE - CHAPMAN DIRECT TESTIMONY |
| 10/29/10 | 201010-55994-02 | AVON TOWNSHIP | TESTIMONY--LETTER TO JUDGE HEYDINGER FILING TESTIMONY OF R. BRESNAHAN |
| 10/29/10 | 201010-55994-01 | AVON TOWNSHIP | TESTIMONY--DIRECT TESTIMONY OF RICHARD J. BRESNAHAN |
| 10/29/10 | 201010-56017-01 | NORTH ROUTE CITIZENS ALLIANCE | TESTIMONY--DIRECT TESTIMONY - SCOTT HYLLA &/OR BRENT SCHMITT |
| 10/29/10 | 201010-56014-02 | INTERVENER SAINT JOHN'S ABBEY/UNIVERSITY | TESTIMONY--MCGEE |
| 10/29/10 | 201010-56014-05 | INTERVENER SAINT JOHN'S ABBEY/UNIVERSITY | TESTIMONY--ROBBINS 1 OF 2 |
| 10/29/10 | 201010-55995-02 | AVON TOWNSHIP | TESTIMONY--SCHEDULES 2 - 5 TO DIRECT TESTIMONY OF KIM A. CHAPMAN |
| 10/29/10 | 201010-56014-01 | INTERVENER SAINT JOHN'S ABBEY/UNIVERSITY | TESTIMONY--LETTER |
| 10/29/10 | 201010-55995-03 | AVON TOWNSHIP | TESTIMONY--LETTER TO JUDGE HEYDINGER DIRECT TESTIMONY OF KIM A. CHAPMAN |
| 10/25/10 | 201010-55763-01 | COURT REPORTER | TRANSCRIPTS--PREHEARING ON 9-15-10 |
| 10/25/10 | 201010-55793-01 | DOC OES | NOTICE--OF PUBLIC HEARING |
| 10/19/10 | 201010-55600-01 | NOCAPX 2020 -UNITED CITIZENS ACTION NETWORK - NORTH ROUTE CITIZENS ALLIANCE | COMMENTS--AND EX A D E - MINOR CORRECTION TO LETTER |
| 10/18/10 | 201010-55575-01 | MINNESOTA DEPARTMENT OF TRANSPORTATION | COMMENTS |
| 10/18/10 | 201010-55586-02 | NOCAPX 2020 -UNITED CITIZENS ACTION NETWORK - NORTH ROUTE CITIZENS ALLIANCE | COMMENTS--EXHIBIT B AIRPORTS |
| 10/18/10 | 201010-55586-01 | NOCAPX 2020 -UNITED CITIZENS ACTION NETWORK - NORTH ROUTE CITIZENS ALLIANCE | COMMENTS--COMMENT AND EXHIBITS A D AND E |
| 10/18/10 | 201010-55586-03 | NOCAPX 2020 -UNITED CITIZENS ACTION NETWORK - NORTH ROUTE CITIZENS ALLIANCE | COMMENTS--EXHIBIT C EPRI FIBER OPTIC REPORT |
| 10/15/10 | 201010-55523-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | COMMENTS--COMMENT REGARDING THE DRAFT ENVIRONMENTAL IMPACT STATEMENT |
| 10/14/10 | 201010-55446-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | TESTIMONY--LAHR DIRECT TESTIMONY FILING LETTER, CERTIFICATE OF SERVICE, AND OFFICIAL SERVICE LIST |
| 10/14/10 | 201010-55446-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | TESTIMONY--LAHR DIRECT TESTIMONY AND SCHEDULES 1-7 |
| 10/13/10 | 201010-55422-01 | OAH | ORDER--ORDER GRANTING INTERVENTION TO AVON TOWNSHIP AND ST. JOHNS ABBEY UNIVERSITY AND AMENDING PREHEARING ORDER |
| 10/13/10 | 201010-55444-01 | XCEL ENERGY | TESTIMONY--DIRECT COVER |
| 10/13/10 | 201010-55444-02 | XCEL ENERGY | TESTIMONY--DIRECT GERALD CHEZIK |
| 10/12/10 | 201010-55405-01 | ST. JOHN'S ABBEY/UNIVERSITY | LETTER |
| 10/12/10 | 201010-55380-01 | NOCAPX U-CAN AND NORCA | LETTER--- TO JUDGE HEYDINGER - NO OBJECTIONS TO INTERVENTION OR SCHEDULE |
| 10/11/10 | 201010-55378-01 | NORTHERN STATES POWER COMPANY | REQUEST TO UPDATE SERVICE LIST--ADD BRAMA |
| 10/11/10 | 201010-55327-01 | NORTHER STATES POWER COMPANY AND GREAT RIVER ENERGY | LETTER |
| 10/11/10 | 201010-55375-01 | OAH | LETTER--SCHEDULE FOR FILING TESTIMONY |
| 10/08/10 | 201010-55266-01 | OTTER TAIL POWER COMPANY | REQUEST TO UPDATE SERVICE LIST--ADD SMESTAD |
| 10/07/10 | 201010-55243-01 | AVON TOWNSHIP | INTERVENTION--NOTICE OF APPEARANCE |
| 10/07/10 | 201010-55261-03 | ST. JOHN'S ABBEY/UNIVERSITY | NOTICE OF APPEARANCE--LETTER |
| 10/07/10 | 201010-55261-02 | ST. JOHN'S ABBEY/UNIVERSITY | NOTICE OF APPEARANCE--PETITION FOR INTERVENTION |
| 10/07/10 | 201010-55243-03 | AVON TOWNSHIP | INTERVENTION--LETTER TO JUDGE HEYDINGER |
| 10/07/10 | 201010-55261-04 | ST. JOHN'S ABBEY/UNIVERSITY | NOTICE OF APPEARANCE--CERT OF SERVICE |
| 10/07/10 | 201010-55243-04 | AVON TOWNSHIP | INTERVENTION--CERTIFICATE OF SERVICE |
| 10/07/10 | 201010-55261-01 | ST. JOHN'S ABBEY/UNIVERSITY | NOTICE OF APPEARANCE--NOTICE |
| 10/07/10 | 201010-55243-02 | AVON TOWNSHIP | INTERVENTION--PETITION TO INTERVENE |
| 10/06/10 | 201010-55221-01 | OAH | ORDER---GRANTING INTERVENTION TO NOCAPX2020, UNITED CITIZENS ACTION GROUP AND NORTH ROUTE CITIZENS ALLIANCE |
| 09/24/10 | 20109-54804-01 | NOCAPX 2020 U-CAN AND NORCA | INTERVENTION--AMENDED PETITION TO INTERVENE |
| 09/14/10 | 20109-54440-01 | NOCAPX U-CAN AND NORTH ROUTE CITIZENS ALLIANCE | INTERVENTION--COVER LETTER, NOTICE OF APPEARANCE AND PETITION FOR INTERVENTION |
| 09/07/10 | 20109-54163-01 | COURT REPORTER | TRANSCRIPTS--PREHEARING CONFERENCE HELD ON 5-18-10 ST PAUL |
| 09/03/10 | 20109-54126-01 | DOC OES | NOTICE--OF AVAILABILITY OF DEIS AND PUBLIC INFO MTG |
| 09/02/10 | 20109-54087-07 | DOC OES | OTHER--DEIS - APP. H - MAPS 61-80 |
| 09/02/10 | 20109-54087-09 | DOC OES | OTHER--DEIS - APPENDICES I-K |
| 09/02/10 | 20109-54087-02 | DOC OES | OTHER--DEIS - APPENDICES A-G |
| 09/02/10 | 20109-54087-08 | DOC OES | OTHER--DEIS - APP. H - MAPS 81- 102 |
| 09/02/10 | 20109-54087-05 | DOC OES | OTHER--DEIS - APP. H - MAPS 21-40 |
| 09/02/10 | 20109-54087-04 | DOC OES | OTHER--DEIS - APP. H - MAPS 1-20 |
| 09/02/10 | 20109-54087-06 | DOC OES | OTHER--DEIS - APP. H - MAPS 41-60 |
| 09/02/10 | 20109-54087-01 | DOC OES | OTHER--DRAFT ENVIRONMENTAL IMPACT STATEMENT - MAIN DOCUMENT |
| 09/02/10 | 20109-54087-03 | DOC OES | OTHER--DEIS - APP. H - MAPS INDEX |
| 08/19/10 | 20108-53643-01 | OAH | LETTER--REGARDING 9-15-10 TELEPHONE CONFERENCE |
| 07/16/10 | 20107-52658-02 | DOC OES | NOTICE--ENVIRONMENTAL IMPACT STATEMENT SCOPING DECISION AMENDMENT |
| 07/16/10 | 20107-52658-01 | DOC OES | NOTICE--NOTICE TO LANDOWNERS |
| 07/15/10 | 20107-52627-01 | DOC OES | OTHER--EIS SCOPING DECISION AMENDMENT |
| 06/29/10 | 20106-52045-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | LETTER--COVER |
| 06/29/10 | 20106-52045-02 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | LETTER--MAPS |
| 06/29/10 | 20106-52045-03 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | LETTER--CERT OF SERVICE |
| 06/16/10 | 20106-51627-01 | DOC OES | ORDER--PREHEARING ORDER |
| 06/09/10 | 20106-51396-02 | DOC OES | NOTICE--AOS-NOTICE TO LANDOWNERS ON ALTERNATIVE ROUTES |
| 06/09/10 | 20106-51396-01 | DOC OES | NOTICE--NOTICE TO LANDOWNERS ON ALTERNATE ROUTES |
| 05/25/10 | 20105-50786-01 | OAH | LETTER--RE: PREHEARING ORDER |
| 05/25/10 | 20105-50771-01 | OAH | ORDER--PREHEARING |
| 05/21/10 | 20105-50698-01 | NORTHERN STATES POWER COMPANY ON BEHALF OF ITSELF AND ITS CO-APPLICANT GREAT RIVER ENERGY | LETTER |
| 05/18/10 | 8916 | OAH | EXHIBITS - HEARING--EXHIBIT 1B |
| 05/18/10 | 8917 | OAH | EXHIBITS - HEARING--EXHIBIT 11D PART 1 |
| 05/18/10 | 8918 | OAH | EXHIBITS - HEARING--EXHIBIT 11D PART 2 |
| 04/19/10 | 20104-49276-04 | DOC OES | PUBLIC COMMENT--SCANCOMMENTS PT. 4 OF 6 |
| 04/19/10 | 20104-49276-05 | DOC OES | PUBLIC COMMENT--SCANCOMMENTS PT. 5 OF 6 |
| 04/19/10 | 20104-49282-02 | DOC OES | PUBLIC COMMENT--NORCA COMMENTS PT. 2 OF 3 |
| 04/19/10 | 20104-49272-01 | DOC OES | PUBLIC COMMENT--ECOMMENTS PT. 1 OF 3 |
| 04/19/10 | 20104-49276-06 | DOC OES | PUBLIC COMMENT--SCANCOMMENTS PT. 6 OF 6 |
| 04/19/10 | 20104-49276-03 | DOC OES | PUBLIC COMMENT--SCANCOMMENTS PT. 3 OF 6 |
| 04/19/10 | 20104-49276-02 | DOC OES | PUBLIC COMMENT--SCANCOMMENTS PT. 2 OF 6 |
| 04/19/10 | 20104-49272-03 | DOC OES | PUBLIC COMMENT--ECOMMENTS PT. 3 OF 3 |
| 04/19/10 | 20104-49282-03 | DOC OES | PUBLIC COMMENT--NORCA COMMENTS PT. 3 OF 3 |
| 04/19/10 | 20104-49277-01 | DOC OES | PUBLIC COMMENT--PUBLIC MEETINGS RECORDS |
| 04/19/10 | 20104-49272-02 | DOC OES | PUBLIC COMMENT--ECOMMENTS PT. 2 OF 3 |
| 04/19/10 | 20104-49276-01 | DOC OES | PUBLIC COMMENT--SCANCOMMENTS PT. 1 OF 6 |
| 04/19/10 | 20104-49282-01 | DOC OES | PUBLIC COMMENT--NORCA COMMENTS PT. 1 OF 3 |
| 04/19/10 | 20104-49277-02 | DOC OES | PUBLIC COMMENT--MNDOT AND MDNR COMMENTS |
| 04/15/10 | 20104-49178-01 | DOC OES | NOTICE--OF AVAILABILITY OF EIS SCOPING DECISION |
| 04/15/10 | 20104-49166-01 | DOC OES | OTHER--DIRECTORS EIS SCOPING DECISION |
| 04/09/10 | 20104-48989-01 | NORTHERN STATES POWER AND GREAT RIVER ENERGY | NOTICE OF APPEARANCE |
| 04/07/10 | 20104-48909-01 | NORTHERN STATES POWER COMPANY | NOTICE OF APPEARANCE--DOCKET # 09-246 IS INCORRECT ON DOCUMENT, XCEL IS RESUBMITTING |
| 03/31/10 | 20103-48623-01 | OAH | NOTICE--NOTICE OF PREHEARING CONFERENCE MAY 18, 2010 |
| 03/29/10 | 20103-48523-01 | PUC | PUBLIC COMMENT--initially filed in error as 20103-48217 in 09-246 |
| 03/23/10 | 20103-48265-01 | NORTH ROUTE CITIZENS ALLIANCE | LETTER--LETTER EIS SCOPING |
| 03/22/10 | 20103-48242-01 | DOC OES | OTHER--ADVISORY TASK FORCE REPORT TO OES ON SCOPE OF THE EIS |
| 03/16/10 | 20103-48073-01 | NORTH ROUTE CITIZENS ALLIANCE | COMMENTS--ON ST. CLOUD DRAFT ATF REPORT |
| 01/25/10 | 20101-46377-01 | XCEL ENERGY AND GREAT RIVER ENERGY | REQUEST TO UPDATE SERVICE LIST--ADD CHURCH & MCCALIB -REMOVE POORKER |
| 12/30/09 | 200912-45498-05 | PUC | MINUTES--NOVEMBER 12, 2009 AGENDA MEETING |
| 12/21/09 | 200912-45254-01 | DOC OES-EFP | NOTICE--NOTICE OF PUBLIC INFORMATION & EIS SCOPING MEETINGS |
| 12/14/09 | 200912-45025-01 | PUC | PUBLIC COMMENT--WEEK ENDING 12-11-09 |
| 12/08/09 | 200912-44811-01 | DOC OES | NOTICE OF APPEARANCE--KAREN FINSTAD HAMMEL |
| 12/02/09 | 200912-44622-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | NOTICE OF APPEARANCE |
| 12/01/09 | 200912-44552-03 | NORTHERN STATES POWER COMPANY & GREAT RIVER ENERGY | OTHER--PART 1OF3-(MAPS) |
| 12/01/09 | 200912-44552-01 | NORTHERN STATES POWER COMPANY & GREAT RIVER ENERGY | OTHER--PART 2OF3=CONFIRMATION OF NOTICE-AFFIDAVIT OF MAILING |
| 12/01/09 | 200912-44552-02 | NORTHERN STATES POWER COMPANY & GREAT RIVER ENERGY | OTHER--PART 3OF3- (MAPS) |
| 11/23/09 | 200911-44343-01 | PUC | ORDER--NOTICE AND ORDER FOR HEARING UNDER MINNESOTA RULES CHAPTER 1405 |
| 11/17/09 | 200911-44124-01 | DOC OES | ORDER--DIRECTOR |
| 11/13/09 | 200911-44021-01 | PUC | ORDER |
| 11/09/09 | 200911-43775-01 | PUC | PUBLIC COMMENT |
| 11/04/09 | 200911-43622-01 | DOC OES | COMMENTS--RECOMMENDATIONS ON APPLICATION ACCEPTANCE |
| 10/30/09 | 200910-43391-05 | PUC | NOTICE OF COMMISSION MEETING--NOV. 12, 2009 |
| 10/07/09 | 200910-42585-01 | NORTHERN STATES POWER COMPANY AND GREAT RIVER ENERGY | LETTER--NO MAPS ATTACHED TO THIS EFILIED COPY OF LETTER |
| 10/05/09 | 200910-42520-01 | PUC | PUBLIC COMMENT--WEEK OF SEPT 25, 2009 |
| 10/01/09 | 200910-42408-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX I PART 2 OF 4 |
| 10/01/09 | 200910-42391-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX B PART 2 OF 5 |
| 10/01/09 | 200910-42404-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX F |
| 10/01/09 | 200910-42400-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX C PART 5 OF 5 |
| 10/01/09 | 200910-42407-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX I PART 1 OF 4 |
| 10/01/09 | 200910-42392-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX B PART 3 OF 5 |
| 10/01/09 | 200910-42405-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX G |
| 10/01/09 | 200910-42397-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX C PART 3 OF 5 |
| 10/01/09 | 200910-42403-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX E |
| 10/01/09 | 200910-42409-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX I PART 3 OF 4 |
| 10/01/09 | 200910-42388-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPLICATION |
| 10/01/09 | 200910-42393-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX B PART 4 OF 5 |
| 10/01/09 | 200910-42390-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX B PART 1 OF 5 |
| 10/01/09 | 200910-42402-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX D |
| 10/01/09 | 200910-42411-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX J |
| 10/01/09 | 200910-42389-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX A |
| 10/01/09 | 200910-42395-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX C PART 1 OF 5 |
| 10/01/09 | 200910-42398-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX C PART 4 OF 5 |
| 10/01/09 | 200910-42394-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX B PART 5 OF 5 |
| 10/01/09 | 200910-42406-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX H |
| 10/01/09 | 200910-42411-02 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX L |
| 10/01/09 | 200910-42387-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING |
| 10/01/09 | 200910-42411-03 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX K |
| 10/01/09 | 200910-42410-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX I PART 4 OF 4 |
| 10/01/09 | 200910-42396-01 | XCEL ENERGY AND GREAT RIVER ENERGY | INITIAL FILING--APPENDEX C PART 2 OF 5 |
| 09/29/09 | 20099-42287-01 | PUC | PUBLIC COMMENT |
| 09/22/09 | 20099-42072-01 | PUC | PUBLIC COMMENT--REVISED |
| 09/21/09 | 20099-42041-01 | PUC | PUBLIC COMMENT--COVER INCORRECT-SEE REVISED |